Published date: 18 July 2022

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 7 April 2022, 9am

Contract summary

Industry

  • Construction work - 45000000

Location of contract

BA3 2HQ

Value of contract

£900,000

Procurement reference

Midsomer Norton Town Hall Phase 1 Regeneration - Principal Contractor

Published date

18 July 2022

Closing date

7 April 2022

Closing time

9am

Contract start date

7 June 2022

Contract end date

30 June 2023

Contract type

Works

Procedure type

Open procedure (below threshold)

Any interested supplier may submit a tender in response to an opportunity notice.

This procedure can be used for procurements below the relevant contract value threshold.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Grade II listed Midsomer Norton Town Hall will be the subject of a phased programme of work to restore the historic market hall to its original appearance, improve accessibility to the building as a whole through providing increased level access and circulation, and improve facilities such that it can continue to act as civic and community hub of Midsomer Norton. The work will be phased with Phase 1 (the subject of this notice) focusing on the ground floor Market Hall. The works are subject to the conditions of both the planning consent (21/00914/FUL) and listed building consent (21/00915/LBA). It is anticipated that the contract will be the Joint Contractors Tribunal (JCT) Intermediate. Full details of evaluation criteria and how to apply are shown in the document General Information supplied; however this is summarised as follows: tenders will be evaluated on the basis of 70% cost, 30% quality, Quality is broken down as follows: 5% Approach to Health & Safety; 5% Ability to working flexibly on a live site; 5% Programme; 5% Climate Emergency (see Section 4, Supplier Questionnaire); 10% Experience of similar projects on listed buildings including technical competence of direct labour and subcontractors, and a minimum of three case studies. There is a short supplier questionnaire which must be completed as part of the tender submission. All enquiries/ requests for site visits should be directed to Nicola Dyer, Project Manager - nicola.dyer@greenwoodprojects.com. Please note that all submissions should be addressed to the Town Clerk, townclerk@midsomernortontowncouncil.co.uk.


More information

Previous notice about this procurement

Midsomer Norton Town Hall Phase 1 Regeneration - Principal Contractor

  • Opportunity
  • Published 24 February 2022, last edited 24 March 2022

Attachments


Award information

Awarded date

30 June 2022

Contract start date

29 July 2022

Contract end date

30 June 2023

Total value of contract

£1,095,797

This contract was awarded to 1 supplier.

ANG Artelia

Address

9 Greenfield Crescent
Edgbaston
Birmingham
B15 3AU

Reference

Companies House number: 6646864

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Contact name

Nicola Dyer

Address

Elmfield House, New Yatt Road
Witney
OX28 1PB
England

Telephone

07889 213 838

Email

nicola.dyer@greenwoodprojects.com

Website

https://www.midsomernortontowncouncil.co.uk/