Published date: 31 October 2024
Last edited date: 6 December 2024
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Hydraulic or pneumatic power engines and motors - 42121000
Hydraulic power packs - 42122210
Waste incinerators - 42320000
Consultative engineering and construction services - 71310000
Engineering design services - 71320000
Location of contract
GU24 0NF
Value of contract
£45,000 to £50,000
Procurement reference
BC22-004 WP10
Published date
31 October 2024
Closing date
13 December 2024
Closing time
12pm
Contract start date
3 February 2025
Contract end date
28 November 2025
Contract type
Works
Procedure type
Open procedure (below threshold)
Any interested supplier may submit a tender in response to an opportunity notice.
This procedure can be used for procurements below the relevant contract value threshold.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
The scope of works will involve:
• Detailed design work for the hydraulic system, with all calculations (tank sizing, pump sizing, pipe pressure loss, etc)
• Supply, manufacture, delivery and installation of the hydraulic system
• Overhaul of existing hydraulic rams
• Remove the existing hydraulic system and drain all oil into suitable containers.
• Install the new hydraulic system and connect to the overhauled rams
• Commissioning of hydraulic system in isolation of the control panel.
• Final commissioning with the control panel providing the enabling/disabling signals.
• During the works, the existing hydraulic system and drained oil will remain in the loading hall area. The site team will arrange for this to be taken outside of containment. However, the supplier is to allow costs for:
o Draining all oil from the hydraulic system into suitable containers
o Dismantling the existing hydraulic system so it can be taken out of the fire door (approx. 900mm wide)
o Lift and shift of all items outside of biocontainment
o Disposal of existing hydraulic system and provide all waste certification to the Client Project Manager
• Management of all subcontractors employed by the supplier to complete these works.
• On completion, an O&M is to be submitted which provides details of works from design to completion. The O&M should include all relevant items shown in the PIF and should include all valves/components labelled with a schedule of components included. A separate section which provides details of the following
o Brief Description of the works being carried out.
o Project Risk Assessment.
o Key structural principals.
o Hazardous materials used.
o Information on the future removal of installed plant.
o H&S information about equipment provided for cleaning or maintaining installed plant.
o The nature, location and markings of significant services.
o Information and as built drawings of buildings, plant and equipment.
o Step by step activities to carry out the works.
o Lesson Learnt, challenges met and how they were overcome.
• As part of the works, the supplier should also provide the following:
o All provisions for the installation and deconstruction work, including but not limited to:
All necessary machinery and equipment required for the works.
Provision of lighting if needed during winter months
Provision of transport vehicles required for the works which is not listed as part of the CDM site below.
Provision of weather protection for any equipment and materials used/stored outside.
All PPE required for safe working during all works.
A CDM Construction site will be set up as part of the overall project which will provide for the following:
• Site Supervision
• HERRAS fencing and appropriate signage around CDM area
• Site Office
• Welfare Office including changing areas
• Waste skips
• Scissor lift
• Fork-lift truck / telehandler
• CDM documentation / inductions / daily logs / management of RAMS
More information
Attachments
-
- 1. ITT - WP10 Hydraulic System Replacement Project.docx
- Bidding documents
-
- 2. Appendix A - Supplier Pre-Qualification Questionnaire.docx
- Bid submission documents
-
- 3. Appendix B - Scoring Matrix V1.xlsx
- Evaluation criteria
-
- 4. Appendix C - Pricing Schedule.xlsx
- Bid submission documents
-
- 5. Appendix D - NEC4 ECC OpA Contract Data.docx
- Contract draft
-
- 6. Appendix E - WP10 Hydraulic System Replacement Project.docx
- Technical specifications
-
- 7. Appendix F - Form of Offer.docx
- Bid submission documents
-
- 8. Appendix G - The Pirbright Institutes use of animals in research.pdf
- Bidding documents
-
- 9. Appendix H - Confidentiality Agreement.docx
- Bidding documents
-
- WP10 - Clarifications.xlsx
- Clarifications to bidders questions
Additional text
-
Please note that Appendix H - Confidentiality Agreement must be fully completed, signed, PDFed and emailed to Procurement.Department@pirbright.ac.uk asap. Then and only then will access to the full ITT package (6. Appendix E1 - Site Documents & 6. Appendix E2 - Existing Hydraulic System O&M) be granted to the requester.
Share this notice
Closing: 13 December 2024, 12pm
All content is available under the
