Published date: 27 March 2017
Last edited date: 27 March 2017
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Miscellaneous engineering services - 71330000
Location of contract
West Midlands, London
Value of contract
£0 to £87,420
Procurement reference
PROC.01.0546
Published date
27 March 2017
Closing date
25 January 2017
Contract start date
1 February 2017
Contract end date
31 March 2017
Contract type
Service contract
Procedure type
Open procedure
Any interested supplier may submit a tender in response to an opportunity notice.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Objectives
The targeted review will:
• Provide a comprehensive assessment of asset health reporting which will include the identification of outliers.
• Enable Ofwat to assess whether companies are taking full ownership of, and responsibility for, asset health.
• Evaluate the relative balance of performance and condition monitoring/assessment within the context of new technology.
• Evaluate the assurance which companies receive for new assets.
Scope
The scope of this work includes assessing company's evaluation, management and interventions with regards asset health. Any recommendations for alternative approaches for PR19 should be within the context of the overall framework of a total expenditure approach to cost assessment and the outcomes framework. Recommendations should aim to enhance customer legitimacy, enable cost effective/timely investment and provide assurance for resilience.
Key Tasks
In order to meet the business objectives, the project will involve the Contractor performing the following tasks:
• Attending and leading meetings with all water companies (WASC's/WOC's) at their premises, however we would consider conducting some of the meetings via teleconference. A member of the Ofwat team will aim to support at these meetings.
• Discussions and short debrief with the Ofwat team following each company meeting.
• Input into pre-meeting briefing/information pack for companies as necessary. This may include collecting information from companies before the meeting, too.
• Regular weekly discussions with the Ofwat team regarding the project, next steps and highlighting any areas of concern.
• A weekly email to the project manager concerning budget spent, remaining and forecast expenditure for the remainder of the contract.
• Review of available technology and approaches for performance and condition monitoring.
Key Deliverables
The Contractor will be required to produce the following deliverables:
A draft and final report; detailing the approach and findings of the targeted review. This should be focused on addressing the questions highlighted in this ToR and include findings from discussions with companies and methods of addressing any concerns regarding robustness and consistency of asset health methodology and investment planning. The draft report should be produced no later than 15 March 2017. Earlier versions can be shared and discussed prior to this. We may request that the draft report be presented to a group of Ofwat colleagues.
The final report (a full and a redacted version if required), suitable for publication, should be produced no later than 31 March 2017. Ofwat may wish to disclose the final report separately or as part of a publication. The final report should include recommendations for next steps, particularly on increasing transparency and consistency of standards across the sector.
Award information
Awarded date
31 January 2017
Contract start date
1 February 2017
Contract end date
31 March 2017
Total value of contract
£87,420
This contract was awarded to 1 supplier.
Halcrow Group Limited
Address
Elms House
43 Brook Green
London
W6 7EFReference
None
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Address
Centre City Tower
7 Hill Street
Birmingham
B5 4UA
England
Share this notice
Closing: 25 January 2017
All content is available under the