Published date: 26 March 2025

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 4 August 2021, 12am

Contract summary

Industry

  • Repair work on recreational areas - 45236290

Location of contract

CB23 1JP

Value of contract

£100,000

Procurement reference

SP2021

Published date

26 March 2025

Closing date

4 August 2021

Closing time

12am

Contract start date

4 October 2021

Contract end date

4 October 2022

Contract type

Works

Procedure type

Open procedure (above threshold)

Any interested supplier may submit a tender in response to an opportunity notice.

This procedure can be used for procurements above the relevant contract value threshold.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

The current skate park was built back in 2007 and mainly funded by local business, lottery funding and community support.
The skatepark and land is owned and maintained by the Haslingfield Parish Council.
It is used by all ages, from young children on scooters, to young adults, using skateboards and BMXs. The users are mainly from Haslingfield but also come from surrounding villages, some as far as Royston.
It is used all year round, on weekends during the summer months there are on average of 20 users a day.
There is also a basketball court on site.

CURRENT SITUATION
Unfortunately, due to its age and construction of its time, the skate park is in need of a complete overhaul.
The ramps are mainly constructed out of wood, including the framework and surfaces, overtime these ramps have suffered from wear and tear, from use, resulting in cracks and damage in the wood, allowing moisture to enter thus rotting the structures over time.
The parish council have repaired and replaced various parts of each ramp unit but we have now reached a point of non economic viability, any money spent now on repairs would not last long and the money would be better spent on investing in new ramps and equipment.
The basket ball court is also in need up of updating, the surface is covered in moss and algae which when wet can be very slippery and dangerous. The hoops and nets are broken and rusty.

PLAN
We have spoken to various contractors and obtained prices for like for like ramps, these are sufficient and would be a marked improvement, but what is clear from demand and perhaps a more long term solution would be to invest in a brand new concrete skatepark.
FINANCING
We are in the process of applying for an Amey grant. This grant is on offer for non profit organisations such as ourselves to improve community facilities that are working 10 miles, as the crow flies, from a landfill site. We currently are 7.7 miles from Milton Recycling centre.
This grant is for projects up to £100,000, of which we would have to raise 11%. We currently have this 11% already in place.
NEXT STEPS
We'd now look for you to provide some detailed plans - we're open to ideas and suggestions to best use the space.
Then, costings and timescales for completely renovating our skatepark and installing new concrete ramps, runs and units etc. This could also include other facilities such as covered seating areas etc. as detailed in the demand.
Once we have these plans and details we can submit our application for the grant and hopefully have approval


Site address:
Haslingfield Skatepark
Porkers Lane
Haslingfield
CB23 1JP

Rough Dimensions:
Basketball Court - 17m Long x 13m Wide
Skate Park - 30m Long x 15 Wide


More information

Previous notice about this procurement

Haslingfield Skatepark Renovation

  • Opportunity
  • Published 4 May 2021

Attachments


Award information

Awarded date

14 February 2022

Contract start date

23 May 2023

Contract end date

30 September 2024

Total value of contract

£110,000

This contract was awarded to 1 supplier.

Betongpark

Address

30 Orange Street,
Calder and Co,
London
WC2H 7HF

Reference

Companies House number: 12422626

Value of contract

£110,000

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Contact name

Ben Mavely