Published date: 16 April 2018
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Drainage construction works - 45232450
Location of contract
DN7 6DS
Value of contract
£153,841
Procurement reference
tender_162878/666467
Published date
16 April 2018
Closing date
13 February 2018
Contract start date
14 May 2018
Contract end date
30 June 2018
Contract type
Works
Procedure type
Open procedure
Any interested supplier may submit a tender in response to an opportunity notice.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Natural England (NE) Hatfield Moors, was exploited for peat over many centuries. During the 20th century the integrity of the bog and its unique biodiversity were severely threatened by mechanised peat extraction and associated drainage. These activities finally ended in 2004 and in 2014 a LIFE+ Project restoration (LIFE13NAT/UK/000451) project provided the opportunity to restore and extend the UK's largest area of degraded lowland raised bog providing a long-term future for the rare plants, birds and insects that have evolved to live on this unique wetland habitat.
As part of the Hatfield Moor restoration project it is proposed to incrementally increase local water levels to enable re-establishment of the native peatland species and return the currently drained peat land to a natural habitat. To achieve this, various manmade water channels are to be controlled to impound water and saturate the surrounding peat land. This will be facilitated by the installation of cut-off piles and the provision of adjustable tilting weirs that will enable modification of the upstream water level. Two existing weirs located in sites 3 and 4 are to be retrofitted prior to commencement.
Therefore, the scope of works is as follows; to supply and install 3 tilting weirs around Natural England's Hatfield Moors Peatland site with associated water control valves across the existing drainage ditches, this includes installation of cut-off sheet piling to support the provision of the tilting weirs and installation of hand rails. Additionally, the works will include an aspect of re-profiling earthworks.
NE are the 'Client' with Mott MacDonald acting as the Principal Designer and Project Manager for NE on this project,works to be carried out by the Principal Contractor, who will be the supplier appointed.
Key Objectives are to deliver the project effectively and ensure that project completion and operational use is achieved by the 30th June 2018.
More information
Previous notice about this procurement
Construction of tilting weirs at Hatfield SAC part of Humberhead Peatlands NNR
- Opportunity
- Published 15 January 2018
Additional text
-
Please note that Defra procurement uses an E-tendering system for Procurement activities. This is currently provided by Bravo Solutions. To access appropriate tendering and contractual documents, please access the E-Tendering portal at https://defra.bravosolution.co.uk", ensuring that your registration includes "Defra". If you have any problems with this system, please contact Bravo on their telephone helpline number 0800 368 4850 or by emailing them at help@bravosolution.co.uk.
Award information
Awarded date
26 March 2018
Contract start date
14 May 2018
Contract end date
30 June 2018
Total value of contract
£153,841
This contract was awarded to 1 supplier.
Colwill Contracting Ltd
Address
Hatfield Woodhouse, Doncaster, South Yorkshire, DN7 6NF, UNITED KINGDOM
Reference
None
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Contact name
Natural England
Address
Natural England
Peterborough
PE1 1NG
England
Telephone
00
Share this notice
Closing: 13 February 2018
All content is available under the