Published date: 24 December 2020
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Construction work - 45000000
Location of contract
PO15 7AH
Value of contract
£284,075.97
Procurement reference
OP15799
Published date
24 December 2020
Closing date
9 September 2020
Closing time
2pm
Contract start date
16 November 2020
Contract end date
22 January 2021
Contract type
Works
Procedure type
Call-off from a framework agreement
A mini-competition or direct purchase from a pre-established framework agreement.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
The project involves refurbishment of a two-storey office
building in Fareham. Whilst the building will be vacated during
the course of the works, the contractor will be expected to
proceed with all care and due diligence throughout the duration
of the contract. Works will include but not be limited to the
following:
Building Works
- Demolition/strip out works
- Redecorations
- Flooring replacement
- Suspended ceiling replacement
- Formation of new rooms
- 2 No. Kitchen replacements
- 1 No. cleaners cupboard
- Internal door replacement
- External door replacement
- Fire Precaution Works
- External maintenance works
- New car park line marking
Mechanical Works
- Provision of mechanical extract ventilation to the toilet areas
andkitchenettes. Existing ductwork shall be retained where
practical but some systems will require entirely new ductwork
installations.
- The meeting room shall have fresh air heat recovery.
- The existing ground and first floor toilet areas are to be
remodelled and will require new domestic services.
- The ground floor kitchen and first floor kitchenette will
require modifications to the domestic services, including
installation of hot water boilers and hot water heaters.
- The existing shower room will be remodelled and converted to
a cleaner's cupboard.
- The existing electric radiators shall be stripped out and
replaced with new electric radiators.
- The comfort cooling unit and associated refrigeration
pipework serving the existing first floor meeting room shall be
decommissioned and stripped out.
- The Mechanical contractor shall be responsible for stripping
out redundant mechanical services and plant.
Award information
Awarded date
8 October 2020
Contract start date
16 November 2020
Contract end date
22 January 2021
Total value of contract
£284,075.97
This contract was awarded to 1 supplier.
Dorelbury Ltd
Address
Crompton Way
Segensworth West
Fareham
Hampshire
PO15 5SSReference
Companies House number: 1519295
Value of contract
£284,075.97
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Contact name
Angela Timlin
Address
The Castle
WINCHESTER
SO238ZB
England
Share this notice
Closing: 9 September 2020, 2pm