Published date: 24 June 2025
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Prison building construction work - 45216113
Location of contract
GL12 8BT
Value of contract
£995,637
Procurement reference
tender_436486/1484911
Published date
24 June 2025
Closing date
11 June 2024
Closing time
5pm
Contract start date
13 May 2025
Contract end date
31 May 2027
Contract type
Works
Procedure type
Call-off from a framework agreement
A mini-competition or direct purchase from a pre-established framework agreement.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
HMP Leyhill has an old copper pipework infrastructure from the plant rooms to the wing and steel heating loops. All pipework feeding the heating's loops are below ground in a vaulted floor with very limited access. This comes up above the floor to the steel heating loop supplying heating to the cells on all spurs to A & B wings. (385 spaces). The pipework is over 40 years old & has worn so thin that it is regularly being perforated & leaking.
Contractors are struggling to access the fractures & are having to cut access hatches into the concrete floor, where they can access the pipework. The pipework is often too thin to affect a repair & must be cut back several times before they are able to make a connection. The repair increases pressure & often cause a further leak a meter along the pipe within a very short period of time.
There have been several leaks recently and as the Living block has no spare electrical capacity for emergency heaters & installing a generator close by would be noisy. Potentially we could be looking at a decant of a complete wing if the infrastructure is not addressed prior to a complete failure.
A constructor has been appointed for the design and build of the project.
This is a two stage Design and Build Contract let under the PPC2000 (Amended 2013) Form of contract.
The original estimated value of the contract was calculated by MOJ, and its Cost Consultants following desktop and non-intrusive surveys and was based on information reasonably known at the time and arrived at via a thorough and appropriate methodology. The first stage will involve the constructor providing Pre-construction surveys and design services at a cost of £172,758.43.
Award information
Awarded date
13 May 2025
Contract start date
13 May 2025
Contract end date
31 May 2027
Total value of contract
£995,637
This contract was awarded to 1 supplier.
Kier Construction Ltd
Address
2nd Floor, Optimum House, Clippers Way, Salford, M50 3XP
Reference
No reference - other
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Address
102 Petty France
London
SW1H 9AJ
England
Share this notice
Closing: 11 June 2024, 5pm