Industry

  • Prison building construction work - 45216113

Location of contract

GL12 8BT

Value of contract

£995,637

Procurement reference

tender_436486/1484911

Published date

24 June 2025

Closing date

11 June 2024

Closing time

5pm

Contract start date

13 May 2025

Contract end date

31 May 2027

Contract type

Works

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

HMP Leyhill has an old copper pipework infrastructure from the plant rooms to the wing and steel heating loops. All pipework feeding the heating's loops are below ground in a vaulted floor with very limited access. This comes up above the floor to the steel heating loop supplying heating to the cells on all spurs to A & B wings. (385 spaces). The pipework is over 40 years old & has worn so thin that it is regularly being perforated & leaking.

Contractors are struggling to access the fractures & are having to cut access hatches into the concrete floor, where they can access the pipework. The pipework is often too thin to affect a repair & must be cut back several times before they are able to make a connection. The repair increases pressure & often cause a further leak a meter along the pipe within a very short period of time.

There have been several leaks recently and as the Living block has no spare electrical capacity for emergency heaters & installing a generator close by would be noisy. Potentially we could be looking at a decant of a complete wing if the infrastructure is not addressed prior to a complete failure.

A constructor has been appointed for the design and build of the project.
This is a two stage Design and Build Contract let under the PPC2000 (Amended 2013) Form of contract.
The original estimated value of the contract was calculated by MOJ, and its Cost Consultants following desktop and non-intrusive surveys and was based on information reasonably known at the time and arrived at via a thorough and appropriate methodology. The first stage will involve the constructor providing Pre-construction surveys and design services at a cost of £172,758.43.


Award information

Awarded date

13 May 2025

Contract start date

13 May 2025

Contract end date

31 May 2027

Total value of contract

£995,637

This contract was awarded to 1 supplier.

Kier Construction Ltd

Address

2nd Floor, Optimum House, Clippers Way, Salford, M50 3XP

Reference

No reference - other

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Address

102 Petty France
London
SW1H 9AJ
England

Email

categorymanagementestatesteam@justice.gov.uk