Published date: 12 June 2017
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Demolition work - 45111100
Landscaping work - 45112700
Footpath construction work - 45233161
Cycle path construction work - 45233162
Coastal-defence works - 45243000
Location of contract
PO1 2BJ
Value of contract
£10,500,000
Procurement reference
P00002507 - AWARD
Published date
12 June 2017
Closing date
17 October 2016
Contract start date
1 April 2017
Contract end date
1 February 2019
Contract type
Works
Procedure type
Restricted procedure
A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
Portsmouth City Council - the 'Authority' - is embarking upon a major programme of coastal defence construction. The programme of works is part of the North Portsea Island Coastal Flood Defence Scheme which aims to reduce the risk of coastal flooding and erosion to the area over the next 100 years.
The Authority is now seeking to appoint a contractor via this procurement exercise to deliver Phase 3 of the programme which will cover flood defence works at Tipner Lake from the Mountbatten Centre, Twyford Avenue to the Ports Creek Roundabout.
The Tipner Lake works will consist of the construction of a new reinforced concrete seawall along the full length of this frontage, which is approximately 1.85km in length. The works will comprise a combination of: c. 300mm thick seawall encasement of the existing defences to extend below the existing foreshore level; replacement of the seawall in the southern area of the site where the existing wall is showing signs of structural movement and is considered of too poor a condition to encase; and local re-alignment of the frontage in this southern area where required. There is the opportunity to create a terraced embankment, an environmental zone, seaward of the defences to the north of the site.
The scope of the works at summary level comprise of the following elements, but may not be limited to;
o Demolition and removal of existing seawall in the southern section of the site;
o Construction of vertical reinforced seawall, including sheet pile and bearing pile installation with local realignment;
o Encasement of the existing seawall in the northern area of the site;
o The existing footpath / cycleway behind the seawall will be reconstructed as part of the works;
o Landscape works to provide appropriate & separate external spaces, including new access points to a public footpath.
The target construction commencement date for the Tipner Lake works is April 2017 with a completion date of October 2018, excluding landscaping works which must be completed by February 2019. It is envisaged that the form of contract used will be NEC 3 ECC Option C. The exact form of contract will be confirmed within the tender documents.
The closing date for receipt of your expression of interest is given against the heading entitled - Date documents can be requested until.
Award information
Awarded date
7 April 2017
Contract start date
1 April 2017
Contract end date
1 February 2019
Total value of contract
£0
This contract was awarded to 1 supplier.
Raymond Brown Construction Ltd
Address
160 Christchurch Road, Ringwood, Hampshire, United Kingdom, BH24 3AR
Reference
None
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Contact name
Procurement Service
Address
Guildhall Square
Portsmouth
Hampshire
PO1 2BJ
United Kingdom
Telephone
023 9268 8235
Share this notice
Closing: 17 October 2016