Published date: 29 March 2021

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 26 February 2021, 2pm

Contract summary

Industry

  • Calculation of costs, monitoring of costs - 71244000

Location of contract

Any region

Value of contract

£18,812.83

Procurement reference

tender_198985/946831

Published date

29 March 2021

Closing date

26 February 2021

Closing time

2pm

Contract start date

8 March 2021

Contract end date

31 March 2021

Contract type

Service contract

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

The A303 Stonehenge project has been asked to investigate the impacts of adding emergency refuges or an additional hard shoulder within in the Stonehenge tunnel in order to increase tunnel safety over the 3km bored tunnels. This requires an assessment of the incremental cost and schedule versus the current baseline scheme (D2AP tunnel without refuges or hard shoulder).
Two options are to be considered:
- The provision of two lay-byes per tunnel, spaced at 1000m centres (four in total), constructed using SCL techniques, to provide an emergency refuge during traffic emergencies / incidents.
- Increasing the diameter of the tunnels to incorporate a hard shoulder lane over the entire length of the tunnel

The incremental cost and schedule impacts are to be measured vs the current baseline scheme design. This will require establishing a baseline estimate and schedule with a consistent set of assumptions against which the above options can be compared. The assessment is to include development of design and methodology assumptions in consultation with the A303 Stonehenge project team so that the assessment has a robust design, methodology and schedule basis.

The assessment is to include the following activities
- Mobilisation and collection of reference design information for the baseline scheme and definition of the above options
- Confirm scope of assessment and output requirements with the A303 Stonehenge project
- Establishment of cost and schedule estimate for the baseline scheme
- Identification of design and construction methodology for the emergency refuge option
- Identification of design and construction methodology for the emergency refuge option

- Production of cost estimates and outline schedule for each option
- Comparison with baseline scheme and identification of incremental impacts
- Production of report to capture impacts and the design / methodology assumptions. This is to include commentary on risks to delivery of the options.
- Presentation of findings

No design cross sections are available for the above options at this time and these are to be developed as part of the assessment. The level of detail within the assessment should be commensurate a concept design / PCF Options Stage 1 level.


More information

Attachments


Award information

Awarded date

8 March 2021

Contract start date

8 March 2021

Contract end date

31 March 2021

Total value of contract

£18,813

This contract was awarded to 1 supplier.

Benchmark Estimating

Address

Manchester

Reference

No reference - other

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Address

The Cube
Birmingham
B1 1RN
England

Email

cpspf@highwaysengland.co.uk