Published date: 1 August 2017

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 7 July 2017

Contract summary

Industry

  • Fabrication work - 45255400

Location of contract

Yorkshire and the Humber

Value of contract

£120,000

Procurement reference

WDH001-DN278434-85587705

Published date

1 August 2017

Closing date

7 July 2017

Contract start date

26 August 2017

Contract end date

31 March 2020

Contract type

Service contract

Procedure type

Other:

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

The successful tenderer will be require to supply and install handrails as per the drawings located in separe documents attached.

Handrails 2016 01
Handrails 2016 02
Handrails 2016 03

All railings are to be galvanised and a white powder coat finish is to be applied.

All members shall be finished galvanised. It is important that cutting or drilling should be undertaken before the elements forming the frame have been galvanised. The steel tube must be in accordance with BS EN 10255. Hot dip galvanising shall be carried out in accordance to BS EN ISO 1461:2009 and the manufacturers shall supply WDH with certification of the galvanising carried out. The white powder coating shall be carried out in accordance with BS EN 12206 and finally all fabrication work shall be carried out in accordance with British Standards.

Handrails are to be fixed to the ground with lateral support as shown in the specification drawings attached.

Process of the work should follow the process below;

• WDH allocate purchase order number to the successful tenderer
• The successful tenderer attends site within 24 hours to survey.
• The successful tenderer completes fabrication work.
• The successful tenderer arranges the steel to be galvanised
• The successful tenderer arranges the galvanised steel to be coated in white powder
• The successful tenderer attends site and installs the handrail
• The successful tenderer notifies WDH that the order is complete with 10 working days.

Tenderers are encouraged to submit proposals to the above that could reduce the time taken from purchase order allocation to work completion. Tenderers are also encouraged to provide supply chain arrangement they have in place to support the 10 working day turnaround.

Prices and discounts must be inclusive of all charges (examples including, but not limited to supply, galvanisation, undercoat, installation and carriage) and be clearly stated in Appendix 3, no extra delivery or minimum order restrictions will be acceptable and all prices must be fixed for the first 12 months.


Award information

Awarded date

1 August 2017

Contract start date

14 August 2017

Contract end date

13 August 2020

Total value of contract

£100,200

This contract was awarded to 3 suppliers.

KSW Engineering

Address

1 Grantley Way, Wakefield WF1 4PY

Reference

None

Supplier is SME?

No

Supplier is VCSE?

No

M Allens and Sons

Address

165 Snydale Rd, Normanton WF6 1PA

Reference

None

Supplier is SME?

No

Supplier is VCSE?

No

P and W Site Fixing Ltd

Address

Innovation Square, Featherstone, Pontefract WF7 6NX

Reference

None

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Contact name

Mark Whitehouse

Address

Merefield House
Whistler Drive
Castleford
WF10 5HX
United Kingdom

Telephone

+44 1977788679

Email

mwhitehouse@wdh.co.uk

Website

http://www.wdh.co.uk