Published date: 23 July 2021

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 9 April 2021, 12pm

Contract summary

Industry

  • Construction materials and associated items - 44100000

  • Building construction work - 45210000

Location of contract

So17 1bj

Value of contract

£144,125 to £144,126

Procurement reference

2021UoS-0293

Published date

23 July 2021

Closing date

9 April 2021

Closing time

12pm

Contract start date

27 April 2021

Contract end date

30 September 2021

Contract type

Works

Procedure type

Other: Closed Invite Only

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

The University seeks to appoint a contractor to carry out works that comprise the strip out of the ground floor entrance and part of the first floor of Building B60 and construction works required to fit out these areas for the Zepler Institute.


Award information

Awarded date

16 April 2021

Contract start date

27 April 2021

Contract end date

30 September 2021

Total value of contract

£144,125

This contract was awarded to 1 supplier.

BRYMOR CONSTRUCTION LTD.

Address

Brymor House,Forest Road Parklands Business Park
WATERLOOVILLE
Hampshire
PO7 6XP
GB

Reference

Companies House number: 02099201

Value of contract

£144,125

Supplier is SME?

Yes

Supplier is VCSE?

No


About the buyer

Contact name

Michael Goff

Address

BUILDING 37, HIGHFIELD CAMPUS,UNIVERSITY ROAD
SOUTHAMPTON
SO171BJ
England

Telephone

023 8059 2654

Email

m.d.goff@soton.ac.uk