Published date: 6 July 2023

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 1 April 2023, 12pm

Contract summary

Industry

  • Construction work - 45000000

  • Repair and maintenance services - 50000000

Location of contract

England

Value of contract

£81,308.58

Procurement reference

KENT001-DN678044-60526556

Published date

6 July 2023

Closing date

1 April 2023

Closing time

12pm

Contract start date

26 April 2023

Contract end date

21 February 2024

Contract type

Works

Procedure type

Other

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

Stakeholder engagement and the preparation of the Options Report. Subsequent stages include the preparation of Detail Works information, Specifications, Bills of Quantity, Pre-construction Information for the Preliminary and Detailed Design and the deck replacement work on Grove Ferry Bridge, but these will be priced separately.

This is to reconstruct the bridge to the current DMRB CG300 standard as the refurbishment option has been previously rejected.


Award information

Awarded date

1 April 2023

Contract start date

26 April 2023

Contract end date

21 February 2024

Total value of contract

£81,308.58

This contract was awarded to 1 supplier.

AECOM

Address

AECOM Aldgate Tower, 2 Leman Street, London E1 8FA

Reference

None

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Contact name

Adam Chilvers

Address

Invicta House
Maidstone
ME14 1XX
United Kingdom

Telephone

+44 3000415251

Email

adam.chilvers@kent.gov.uk

Website

http://www.kent.gov.uk