Contract summary
Industry
Agricultural, farming, fishing, forestry and related products - 03000000
Location of contract
South West
Value of contract
£8,000 to £10,000
Procurement reference
NEWL003 - Lot 3
Published date
16 August 2018
Closing date
3 September 2018
Contract start date
10 September 2018
Contract end date
21 December 2018
Contract type
Service contract
Procedure type
Competitive quotation (below threshold)
The buyer selects a group of potential suppliers to invite to tender.
This procedure can be used for procurements below the relevant contract value threshold.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Newlyn Pier and Harbour Commissioners is seeking to secure the services of a suitably qualified BREEAM Assessor to work with the design and construction team/s to achieve BREEAM Excellent status for all ERDF funded elements of Newlyn Harbour Regeneration.
The deadline for responses is: 13:00, Monday 3 September 2018.
Newlyn is the largest fishing port in England by fleet and landings. It is located near Penzance in Mounts Bay, South West Cornwall. This Trust Port has a long term programme of development and expansion already underway. These plans address a longstanding shortage of good quality workspace in Newlyn, and quayside workspace in Cornwall, with the construction of industrial workshops, marine engineering infrastructure, food processing facilities and office space.
This contract, will cover three projects within the overall programme: the New Strand, Canner Slipway and Canner Car Park project which together provide regeneration of the centre of the harbour estate and town.
• The New Strand plans are for 2,160 m2 of new flexible workspace with some of this on an upper floor. The buildings will be formed using steel portal frames with lightweight cladding systems to fit with the existing vernacular of the harbour, maximise the flexibility of long term use and minimise build time and disruption to tenants. The current estimate for New Strand project, both building construction and piled foundations, is £3.1m.
• Canner Slipway is the installation of a new quay wall expanding on an existing area of hardstanding to a total area of 2,228m2 that will accommodate 6 to 8 industrial sheds of 120m2 each.
• Canner Car Park will maintain the car parking capacity required by the harbour through demolition of redundant buildings replaced by the New Strand facilities and landscaping.
These three projects are being funded by the Newlyn Pier and Harbour Commissioners, supported by a grant from the European Regional Development Fund (ERDF) under the ESIF Growth Programme for England 2014 to 2020 with the overall cost of all three elements of the scheme estimated at £6,146,308.
More information
Additional text
-
The timelines for the ITT are as follows:
Bidders are asked to register their interest and request a tender pack by 22 August. Tender packs will be sent out from Monday 20 August.
ITT advertised on Contracts Finder: Thursday 16 August 2018.
Potential bidders to request ITT pack by 17.00 on Wednesday 22 August 2018.
Bidders to submit questions (if any) regarding ITT by e-mail to the Programme Manager. Responses will be shared with all bidders. Deadline for questions: 17.00 on Wednesday 29 August 2018.
ITT CLOSING DATE AND TIME: 13.00 on Monday 03 September 2018.
Interviews (if required): First week of September 2018.
About the buyer
Contact name
Lucy Parsons
Address
The Strand, Newlyn
PENZANCE
TR185HW
England
Telephone
01736 362523
programmemanager@newlynharbour.com
Website
Share this notice
Closing: 3 September 2018
All content is available under the