Published date: 21 March 2017
This notice was replaced on 6 November 2017
This notice does not contain the most up-to-date information about this procurement. The most recent notice is:
Awarded contract (published 6 November 2017)
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Office block construction work - 45213150
Refurbishment work - 45453100
Location of contract
RG12 1JD
Value of contract
£2,000,000 to £2,300,000
Procurement reference
CATSRR
Published date
21 March 2017
Closing date
10 April 2017
Contract start date
2 October 2017
Contract end date
9 February 2018
Contract type
Works
Procedure type
Restricted procedure
A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
Yes
Description
Expressions of interest are invited from organisations with demonstrable previous experience of large occupied office refurbishment projects of similar size and scope to this proposed project at Bracknell Forest Council's (the Council's) Time Square premises.
The project will allow the rationalisation of the Council's property portfolio and needs to relocate its staff, Management suite and the Council Chamber and associated democratic function into Time Square.
The Time Square building is a five storey office block located in the centre of Bracknell, and is currently in use as Council Offices.
Estimated contract value between £2m and £2.3m.
For further information, see "Additional text".
More information
Links
-
- www.businessportal.southeastiep.gov.uk
- Procurement plan
- For documents see South East Business Portal
Additional text
-
(Description continued)
The front of the building is deemed to face due east. The building has glazed terraced projections at 4 of the 5 floor levels.
The building is a reinforced concrete / steel framed structure, with a combination of curtain walling to the front and part rear elevations, and brick panel walling to the end and part rear elevations.
There is a flat roof which contains a plant area enclosed by grilles to the perimeter. There are two lift motor rooms mounted on the roof. Access to the roof is currently via a fixed ladder and roof access hatch located in a stairwell to the northern end of the building. The roof has recently been re-covered and roof top mechanical plant replaced.
There is an underground car park beneath the building, accessed via a ramp to the northern face of the building. There are various external staircases into the basement located around the perimeter of the building.
To the front of the building there is a projecting glazed atrium extending for the full height of the building.
The building was (internally) refurbished during 2013, excluding the atrium area.
Council staff are currently located in both Time Square and Easthampstead House both of which are in Bracknell Town Centre. . In order to accommodate the extra staff and a new Management suite and a Council Chamber and associated democratic function into Time Square further changes are required and include :
• The replacement of the main entrance atrium glazing, new atrium roof structure, deck and coverings. Atrium floor plate extension to all floor levels
• New Council Chambers to the Ground Floor along with internal alterations to the ground floor layout.
• Alterations to the fourth floor layout.
• New archive storage facility within the basement area.
• New flag pole and public notice board.
Programme:
Evaluation of the Selection Questionnaires will be completed by end of May 2017.
The tender documents will be issued to the selected contractors by Mid-June 2017 with a 4 week tender period.
The successful contractor will be appointed Mid-September 2017.
The main construction works will commence early October 2017and complete in early February 2018.
The works will be fully designed by The Councils consultant up to RIBA Stage F. The Consultant will then undertake the role as Contract Administrator during the construction phase RIBA Stage K.
Please note that Time Square will be occupied throughout the construction phase. Due care and consideration must be given to ensure that the building functions without any interruptions to service.
Full details of the tender are available on South East Business Portal. In order to receive any clarifications or changes to tender documents organisations must register their interest on the portal. The Council will not be held responsible for not communicating important information
About the buyer
Contact name
Derek Fitz-Gibbon
Address
Bracknell Forest Council
Easthampstead House, Town Square
Bracknell
RG12 1AQ
England
Derek.Fitz-Gibbon@bracknell-forest.gov.uk
Website
Share this notice
All content is available under the
