Published date: 22 February 2023

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 18 November 2022, 2pm

Contract summary

Industry

  • Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork - 45230000

Location of contract

South East

Value of contract

£66,116.90 to £3,441,000

Procurement reference

ET20680

Published date

22 February 2023

Closing date

18 November 2022

Closing time

2pm

Contract start date

13 February 2023

Contract end date

20 October 2023

Contract type

Works

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

A call-off from the Generation 4-TWO 2020 - 2024 Civil Engineering, Highways and Transportation Collaborative Framework (Awarded April 2020).

The scheme is to provide a new cycle route, combining both enhanced shared-use off-road facilities, on-road lanes, improved crossing points. The scheme runs between the Marchwood Road/Bury Lane junction in Eling to the A326 Long Lane / Holbury Drove junction in Holbury, a total distance of over 14km.

This call-off includes Early Contractor Involvement using secondary Option X22 of the NEC4 Engineering and Construction Contract. The works element of the contract will be delivered in Stage Two, within the total £3,441,000 budget.


Award information

Awarded date

12 January 2023

Contract start date

13 February 2023

Contract end date

20 October 2023

Total value of contract

£66,116.90

This contract was awarded to 1 supplier.

MILESTONE INFRASTRUCTURE LIMITED

Address

Abel Smith House,Gunnels Wood Road
STEVENAGE
Hertfordshire
SG1 2ST
GB

Reference

Companies House number: 13007933

Value of contract

£66,116.90

Supplier is SME?

No

Supplier is VCSE?

No

Additional details

£66,116.90 for Stage One, which consists of Early Contractor Involvement (ECI)

£3,441,000.00 is the total budget inclusive for ECI and construction of the works