Description

"Project location: HM Naval Base Portsmouth

The Contractor shall be expected to adhere by the HMNB site security requirements, all Contractors and Sub-Contractors shall be BPSS security vetted and will be required to hold the relevant site security passes. The Contractor shall be expected to hold the following levels of insurance £10m Public Liability, £10m Product Liability, £5m Professional Indemnity.

KBS Maritime - Introduction

KBS Maritime is a joint venture between KBR and BAE Systems, bringing together two global players with a rich heritage of delivering excellence, innovation and reliability. The joint venture will combine the expertise of KBR as a global leader in infrastructure asset management and services with BAE Systems' experience and capability within Portsmouth Naval Base. KBS Maritime are delivering an ambitious, modern and enduring change to the Portsmouth Naval base infrastructure, securing investment in the local community and ensuring fit-for-purpose, world-leading fleet support for the Royal Navy and the UK in the decades ahead.

Project Opportunity

KBS Maritime have a requirement for cofferdams that need to be installed on the outer-stops at three locations: B-Lock east, B-Lock west, and A-Lock east which will serve as enabling works for planned permanent works to both locks. A 'stoplog' type of cofferdam is the likely preference, which will comprise of a number of modular sections that span the entrance width of the lock, and will fit vertically on top of one another. These would be installed by cranes, and the size of the modules would therefore be determined by crane lifting and ground loading capacity. The lower module for each location will be unique due to the variation in lock entrance profiles, but the upper modules are likely to be interchangeable. The modules will consist of a truss type construction because of the spanning nature of the structure, and rubber seals would be provided at the connections between the modules and the civil works meeting faces at the lock floor and walls. Budget: circa £5m-£8m

Key Dates (approximate)

Expressions of Interest: 15 May 2023
PQQ Evaluation: 31 May 2023
Bidders Selected: 30 June 2023
ITT Published: 31 July 2023
ITT Close: 08 Sept 2023
Construction commencement: 30 Nov 2023
Construction Completion Feb 2024

"


More information

Additional text

If you are interested in this opportunity, please contact Paul Homshaw - at tenders@kbsmaritime.com to request a Pre-Qualification Questionnaire quoting ref EOI A and B Lock Cofferdam


About the buyer

Contact name

Paul Homshaw

Address

Victory Building, Portsmouth Naval Base,
Portsmouth
PO1 3LS
England

Email

Tenders@kbsmaritime.com