Published date: 27 March 2024
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Electrical machinery, apparatus, equipment and consumables; lighting - 31000000
Building services consultancy services - 71315210
Location of contract
TS104RF
Value of contract
£0
Procurement reference
IT-540-71-3079
Published date
27 March 2024
Closing date
12 April 2024
Closing time
12pm
Contract start date
6 May 2024
Contract end date
5 May 2028
Contract type
Service contract
Procedure type
Open procedure (below threshold)
Any interested supplier may submit a tender in response to an opportunity notice.
This procedure can be used for procurements below the relevant contract value threshold.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
The BMS and EMS system currently runs on Siemens Desigo CC and the facility is on the course to being a fully GMP compliant facility. There are currently ten BMS panels on the site with several sensors and control points that feed into these panels from various cleanroom and plant equipment.
Our EMS and BMS systems both use the same sensors for control and monitoring but operate slightly differently. Our EMS system is fully audit trailed and validated yearly to keep this in line with GMP requirements. The EMS monitors all data coming from our clean rooms which monitors the temperature, humidity, airflow, and differential pressure across all four cleanrooms, service corridors and auxiliary areas.
On site we currently have the below equipment and system checks required to be covered under the service agreement
o 4 cleanrooms all fitted with 2 control panels, 4 differential pressure probes along with a temperature and humidity sensor. Each it will need to be fully calibrated annually along with all calibration reports provided.
o We currently have 11 air handlers in total, 5 of these feed into our cleanroom areas while the other 6 units feed into control offices and event areas. All units have 2 fan speed controllers, 7 pressure transmitters, 1 fresh air temperature sensor, 3 temperature humidity sensors and 2 velocity meters. All of which require to be calibrated annually along with calibration reports.
o Differential pressure switches that will need to be inspected to ensure the electrical operation of the circuit is running as it should.
o As well as this, the switch setting must be checked, and you must ensure that it responds to changes in pressure.
o Air and water flow switches that will need to be inspected to ensure the electrical operation of the circuit is running as it should. The switch setting must be checked to ensure that it responds to change in flow. Actuators/Valves/Dampers/Water Meters- Check the operation of actuators across their full stroke and ensure correct positioning over the analogue output range. Ensure actuator limit switches operate correctly along with Check power fail action operates correctly by simulating mains failure. Check valves for leaks and repair where applicable and ensure minimum let-by in the closed position. Check that the valve and damper linkage are fitted securely. Check that damper blades and linkage operates operate correctly throughout their range, without undue stiffness. Advise relevant Building Services Engineer of any mechanical problems.
o Control Checks - Check the stability of all plant visually along with System Operation Checks. Authorisation will be sought from a member of the CPI operational Engineering team prior to isolating any plant, and care will be taken that any checks do not unduly affect environmental conditions. The system will be set to its 'off' condition (where possible) and check correct response of all controlled equipment. Along with Simu...
More information
Links
-
- https://in-tendhost.co.uk/uk-cpi/aspx/
- Additional information on how to apply for this contract
Additional text
-
For more information please see the tender documentation, that is free to access on https://in-tendhost.co.uk/uk-cpi/
Is a Recurrent Procurement Type? : No
About the buyer
Contact name
Daisy Irving
Address
Wilton Centre
Wilton
REDCAR
TS104RF
United Kingdom
Telephone
+44 01740625716
Share this notice