Published date: 14 April 2020
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Construction work - 45000000
Location of contract
South East
Value of contract
£8,000
Procurement reference
BUCKSH001-DN474480-89959577
Published date
14 April 2020
Closing date
10 April 2020
Contract start date
21 April 2020
Contract end date
30 April 2020
Contract type
Works
Procedure type
Restricted procedure
A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
1. To attend site and carry out an environmental clean of the accessible parts of the boiler room. To protect the 'bare brick' contaminated wall with polythene. To arrange for a reassurance air test by an approved laboratory.
2. Once IPS Have removed the plant from the boiler room we will return to strip, remove and dispose of all the obvious asbestos debris to the walls of the boiler room. To vacuum, decontaminate and prepare for air testing. Following a certificate of reoccupation having been issued we will paint the walls of the boiler room with ET150 and label as a hazard. Also to include a return visit to site to drill some unistrut fixing holes as required by IPS.
Award information
Awarded date
14 April 2020
Contract start date
21 April 2020
Contract end date
30 April 2020
Total value of contract
£8,000
This contract was awarded to 1 supplier.
Scancross
Address
Unit 7b Lupton Road, Thame, Oxon, OX9 3SE
Reference
None
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Contact name
Peter Halsey
Address
1) NCO
Walton Street
Aylesbury
HP20 1YQ
England
Telephone
+44 1296382511
Website
Share this notice
Closing: 10 April 2020
All content is available under the