Published date: 27 November 2019
Last edited date: 27 November 2019
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Demolition work - 45111100
Location of contract
W6 9JU
Value of contract
£0
Procurement reference
tender_222621/811383
Published date
27 November 2019
Closing date
19 December 2019
Contract start date
9 March 2020
Contract end date
31 January 2021
Contract type
Works
Procedure type
Open procedure (below threshold)
Any interested supplier may submit a tender in response to an opportunity notice.
This procedure can be used for procurements below the relevant contract value threshold.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
The key demolition activities which form part of the demolition contract are described below:
- Deconstruction and disposal of all remaining fixtures, fittings and building services.
- Demolition and disposal of Lannoy Point.
- Demolition and disposal of Hartopp Point.
- Demolition and disposal of garages and podium.
- Disconnection of mains utilities including all necessary liaison;
- Grading and earthworks to leave the site ready for re-development
- Maintenance of level access to Chasemore House and traffic access through Williams Close.
- Hoarding and securing the site during and on completion of the works.
About the buyer
Address
Hammersmith Town Hall King Street
London
W6 9JU
England
Share this notice
Closing: 19 December 2019