Published date: 5 June 2019

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 24 April 2019

Contract summary

Industry

  • Construction work - 45000000

Location of contract

North West

Value of contract

£3,800,000

Procurement reference

SP/18/1016 - award

Published date

5 June 2019

Closing date

24 April 2019

Contract start date

25 June 2019

Contract end date

20 April 2020

Contract type

Works

Procedure type

Other: (non OJEU) closed ITT stage following publically open EOI stage

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

AWARD FOLLOWING FORMAL EXPRESSIONS OF INTEREST INVITED PRIOR TO THE RUNNING OF A CLOSED TENDER: Lancaster University's Sports Centre, having been completed in 2011, is currently the subject of two phased extensions, Phase 1A and Phase 1B. Phase 1A, a conditioning suite, is under construction on site and due for completion in December 2018. Phase 1B sees the core facilities of the sports centre expanded, with the intention to house a new build, two storey building housing a sports hall, with a first storey plant room, and internal storage in accordance with Sports England guidance. The total footprint of the building is approximately 1911.615m². The University seeks to appoint a Contractor for these works to fulfil both Principal Contractor and Principal Designer responsibilities under the CDM regulations 2015. RIBA Stage 4 information will be available at tender stage. The project must attain a BREEAM rating of Excellent and an EPC A rating. The location of the site is Bailrigg Campus, Lancaster, LA1 4YW. The start on site date for the works is 24th June 2019, with completion by 17th April 2020.


More information

Additional text

The University invited formally structured expressions of interest in the project, before running a closed tender.
University's e-tendering portal: In-Tend
https://in-tendhost.co.uk/lancaster/
DOCUMENTS MUST BE ACCESSED AND SUBMISSIONS MADE VIA THIS PORTAL.
Any clarifications on procedure, documentation or the project generally must be raised through the In-Tend 'correspondence' function.

In-Tend Support:
Phone: 0845 557 8079
E-mail: support@in-tend.com
Web : https://in-tendhost.co.uk/lancaster/aspx/Help


Award information

Awarded date

24 May 2019

Contract start date

24 June 2019

Contract end date

17 April 2020

Total value of contract

£3,997,881.40

This contract was awarded to 1 supplier.

Conlon Construction Ltd

Address

Charnley Fold Lane
Bamber Bridge
Preston
PR5 6BE

Reference

Companies House number: 708997

Supplier is SME?

Yes

Supplier is VCSE?

No


About the buyer

Contact name

Margaret Haynes

Address

University House
LANCASTER
LA14YW
England

Email

m.haynes@lancaster.ac.uk