Published date: 20 December 2022
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Refurbishment work - 45453100
Location of contract
LD1 5LG
Value of contract
£174,718.79
Procurement reference
tender_234110/1160395
Published date
20 December 2022
Closing date
31 August 2021
Closing time
12pm
Contract start date
27 September 2021
Contract end date
31 October 2022
Contract type
Works
Procedure type
Call-off from a framework agreement
A mini-competition or direct purchase from a pre-established framework agreement.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
2nd Floor Powys County Hall Offices
Works will be undertaken within the County Hall building to fit out and refurbish an area on the second floor to accommodate the APHA office facility. It is a minor refurbishment [Limited to furniture rearrangement, two new seating booths, overhauling the blinds, and electrical testing]. The office space will be for approximately 23 full time employees and is approximately 122m2 floor area.
This is a live, operational building and works will be undertaken in close proximity to third parties.
The Principal Contractor will be required to confirm measures to provide suitable boundaries and access routes to segregate and protect third parties and the workforce throughout the works.
External Cabin
Conversion of an existing meeting/ office space into a packing store facility.
Demolition and strip out of existing partitions, floor finishes, wall mounted fixtures/fittings, skirting and some services
Minor alterations and refurbishment on Ground Floor [full decoration, new flooring, internal laboratory grade doors and joinery fittings].
Minor alterations to existing external doors [installation of key code access control and ironmongery]
Replacing existing felt roof [removing existing timber panels and providing replacement insulation]
Minor External Works [cleaning existing hardstanding, timber cladding, soffits and ramps/steps, followed by preservative treatment. Existing external timber window and door frames to be rubbed down and prepared for new coat of paint/ preservative.]
Strengthening the floor in certain areas
The Principal Contractor will be required to confirm measures to provide suitable boundaries and access routes to segregate and protect third parties and the workforce throughout the works.
Working areas, access routes and parking / laydown proposals must be discussed and agreed with the Employer in advance of works commencing
Forward Operating Base
The Contractor is to provide the electrical infrastructure and fibre optic cable duct provision, for the forward operating base. A new LV cable will be required to run to the forward operating base location.
Please note that the Forward operating Base portacabin removal of units A and unit B to be moved to A location, is not part of the project or contract and any drawings which refer to this are there for information relating to other works.
More information
Award information
Awarded date
27 September 2022
Contract start date
27 September 2021
Contract end date
31 October 2022
Total value of contract
£174,718.79
This contract was awarded to 1 supplier.
Mitie FM
Address
Level 12, The Shard, 32 London Bridge Street, London SE1 9SG
Reference
No reference - other
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Address
Trentside Office
Nottingham
NG2 5FA
England
Share this notice
Closing: 31 August 2021, 12pm