Published date: 11 July 2023
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Instrumentation and control equipment - 31682210
Location of contract
East of England
Value of contract
£20,000 to £30,000
Procurement reference
SC31
Published date
11 July 2023
Closing date
11 August 2023
Closing time
5pm
Contract start date
8 November 2023
Contract end date
8 November 2024
Contract type
Works
Procedure type
Other: Private Procurement
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Private procurement rules
Supply chain notices are business-to-business transactions and are not bound by the same rules and restrictions as public sector contracts. The UK government is not responsible for the conduct of such procurement.
Description
Skanska is preparing to deliver the A428 Black Cat to Caxton Gibbet Improvement Scheme on behalf of National Highways. This package is for supplying instrumentation and monitoring solutions as follows;
Measurement of settlement is required at selected earthwork locations as outlined in the Series 600 Numbered Appendices for Earthworks document and scheme specific drawings. Within the series 600 numbered appendices the locations of the instrumentation are shown in Table 6/12.1 and Drawings in Table 6/3-1. The instrumentation shall comprise magnet extensometers and surface settlement monitoring points.
The Contractor shall provide, install, protect and maintain for the duration of the contract the instrumentation indicated in Table 6/12-1 and described in Appendix 6/12. The Contractor shall provide the equipment necessary to monitor the instrumentation. Termination of earthworks monitoring before the end of the contract is only acceptable with the agreement of the Design Organisation.
The instrumentation shall be installed under the supervision of the Design Organisation, by the appointed Instrumentation Contractor. At least two weeks prior to the installation the Contractor shall provide a method statement giving details of the proposed instrumentation and its installation to the Design Organisation. Standard Details of the monitoring points can be found on drawing HE551495-MOTG-HGT-CONWI_CONW-DE-CE-06506.
Instrumentation shall be installed as soon as practical after the earthworks are constructed to full height. The extensometers will be constructed within a borehole, formed from the finished surface level of the earthwork. Settlement monitoring points shall be constructed at the surface of the finished earthwork.
l instrumentation shall have its head level and position monitored to allow potential adjustments, to be agreed with the Design Organisation. Each instrument shall be adequately marked with its reference number.
You will be invited to complete our Request for Information (RFI), conducted on our Oracle Cloud platform. The RFI will only take between 10 & 15 minutes to complete, at the end of the process you will be told if you have been shortlisted. If you have you will be invited to respond to the full Request for Quotation (RFQ), which will be issued shortly after the RFI closes.
Please see attached the link with a project overview - https://nationalhighways.co.uk/our-roads/a428-black-cat-to-caxton-gibbet/
To respond to our expression of interest request, please see this link which will take you to a Microsoft form - https://forms.office.com/r/nTQdtVFTiH
More information
Links
-
- https://forms.office.com/r/nTQdtVFTiH
- Eligibility criteria
- To respond to our expression of interest request, please see the link above which will take you to a Microsoft form.
About the buyer
Contact name
Chloe Hobbs
Address
Maple Cross House,Denham Way, Maple Cross
RICKMANSWORTH
WD39SW
England
Telephone
07392098889
Website
https://nationalhighways.co.uk/our-roads/a428-black-cat-to-caxton-gibbet/
Share this notice
Closing: 11 August 2023, 5pm