Published date: 23 August 2017
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Construction work - 45000000
Location of contract
South East
Value of contract
£6,636,425
Procurement reference
0465
Published date
23 August 2017
Closing date
17 February 2017
Contract start date
27 July 2017
Contract end date
25 January 2020
Contract type
Works
Procedure type
Other:
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
The Edinburgh Way Improvement scheme involves the widening of the corridor through Harlow's Edinburgh Way from Cambridge Road to River Way. Attached to the highway elements are traffic signals works (minor) and a retaining wall construction. The main highway works involve the construction of additional lanes to both the east and westbound carriageways. Amendments to the roundabout at Cambridge Road (east) are also required involving more challenging phasing of Traffic Management. The works are all to be complete around statutory undertakers diversionary works - some of which , to the south, require civil works and liaisons to be undertaken by the Contractor. To try and mitigate some of the issues with the stats an Advanced Works Contract to move the stats from the northern footpath before the main contract commences are planned to be completed by July 2017
Award information
Awarded date
27 July 2017
Contract start date
28 July 2017
Contract end date
25 January 2020
Total value of contract
£6,636,425
This contract was awarded to 1 supplier.
Morgan Sindall Construction and Infrastructure Ltd
Address
Corporation Street
Rugby
Warwickshire
CV21 2DWReference
None
Supplier is SME?
No
Supplier is VCSE?
No
Additional details
-
This contract was awarded under the Eastern Highways Alliance Framework 2 - Ref- 2015/S 144-265234, 29/7/15
About the buyer
Contact name
Commercial Team
Address
County Hall
Chelmsford, Essex
CM1 1JZ
England
Share this notice
Closing: 17 February 2017
All content is available under the