Published date: 5 December 2022

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 22 July 2022, 12pm

Contract summary

Industry

  • Building construction work - 45210000

  • Multi-functional buildings construction work - 45211350

  • Construction work for buildings relating to leisure, sports, culture, lodging and restaurants - 45212000

    • Pavilion construction work - 45212600

Location of contract

SO23 0QQ

Value of contract

£2,150,000 to £2,150,001

Procurement reference

20221205165012-86482

Published date

5 December 2022

Closing date

22 July 2022

Closing time

12pm

Contract start date

2 September 2022

Contract end date

7 August 2023

Contract type

Works

Procedure type

Open procedure

Any interested supplier may submit a tender in response to an opportunity notice.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Winchester City Council (WCC) are seeking a suitably qualified Principal Contractor to construct a new sports pavilion at King George V Playing Fields, Milland Road,
Bar End, Winchester, SO23 0QA.

The greenfield site has been vested in perpetual trust as open land for public
playing fields. The area north of the access road has been demarcated for a new
pavilion development. The playing fields are currently served by two sports
pavilions which do not meet current standards, are not of adequate size and are in a deteriorating state of repair and condition. These existing pavilions are to be
demolished outside of the main works contract.

The project proposes the construction of a modern and compliant two-storey sports
pavilion which will accommodate: a first-floor clubhouse with a kitchen and
external open viewing balcony, ground-floor changing rooms with associated
showers, officials changing, separate toilets, storage, external bike shelter and
bin store. The pavilion will also have a first-floor balcony viewing area.
Landscaping includes alterations to the access route, car parking, drainage, paving and installation of EV chargers together with other associated works.

Stride Treglown Architecture & Design Practice have developed a design which
is attractive, of high quality, efficient and economical to maintain. It is hoped
that the new Pavilion will serve the current and future needs of the clubs, players, officials and spectators of all ages, cultures, abilities and gender.

The works are to be procured and administered under the JCT Design and Build
Contract 2016.

Works must be completed on-site by August 2023 in anticipation of the next football season.

To register for this procurement opportunity and access the documents, please
use the link contained within 'Additional Details' and follow the instructions
1 and 2:
1) Click on "New supplier registration"
2) Complete the Supplier Registration form

If you need any further assistance with registration or have any queries about using the portal, please contact EU Supply as follows:

E-mail: uksupport@eu-supply.com
Telephone: 0800 840 2050 during office hours ONLY (08.00 to 17.00).


More information

Links


Award information

Awarded date

21 November 2022

Contract start date

2 January 2023

Contract end date

2 October 2023

Total value of contract

£2,946,501.33

This contract was awarded to 1 supplier.

Milestone Contracting Limited

Address

3 Beauchamp Court
10 Victors Way
Barnet
EN5 5TZ

Reference

None

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Contact name

Julie Mahoney

Address

Winchester City Council
Colebrook Street, Winchester
SO23 9LJ
ENG

Telephone

+44 1962814908

Email

jmahoney@winchester.gov.uk

Website

https://www.winchester.gov.uk