Published date: 15 March 2020

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 10 April 2020

Contract summary

Industry

  • Construction work - 45000000

Location of contract

UB8 3PH

Value of contract

£10,000,000

Procurement reference

tender_236226/845095

Published date

15 March 2020

Closing date

10 April 2020

Contract start date

2 July 2020

Contract end date

2 July 2021

Contract type

Works

Procedure type

Restricted procedure (above threshold)

A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.

This procedure can be used for procurements above the relevant contract value threshold.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

The Quad North Building (formerly Halsbury/Physics) is a 3 storey, concrete framed building, which was constructed in c. 1970 to house physics laboratories and associated institutional facilities.

There is an adjoining two storey building (The Postgraduate School) at the front of the building, and a single storey, building on the western side of the building, which were both constructed at the same time as the main Quad North Building. In 2003, a large 2 storey extension (The Wolfson Centre) was added at the rear of the building.

The main 3 storey section of the Quad North Building has undergone several cosmetic refurbishments since construction.

As Brunel University are still finalising documents all stage 2 documents are available, however stage 3 documents will be made available in the coming weeks.
Full details are uploaded on www.brunelesourcing.com


About the buyer

Address

Brunel University London
Uxbridge
UB8 3PH
England

Email

Lakshman.Gill@brunel.ac.uk