Contract summary

Industry

  • Concrete pipes and fittings - 44114220

  • Pipeline, piping, pipes, casing, tubing and related items - 44160000

  • Sewer pipes - 44163130

Location of contract

London

Value of contract

£101,000 to £150,000

Procurement reference

C4N55878638

Published date

8 June 2021

Closing date

18 June 2021

Closing time

12pm

Contract start date

25 August 2021

Contract end date

28 August 2022

Contract type

Works

Procedure type

Competitive quotation (below threshold)

The buyer selects a group of potential suppliers to invite to tender.

This procedure can be used for procurements below the relevant contract value threshold.

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.
The Project comprises:
a. tunnels:
i. a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
ii. 11 connection tunnels, which will link flows from CSOs to the main tunnel.
b. Worksites:
i. five main tunnel Worksites (drive and/or reception sites)
ii. 16 CSO Worksites
iii. two System modification Worksites Thames Tideway Tunnel
iv. works at Beckton Sewage Treatment works.

Scope of Works

Temporary works design and provisions
Trench excavations
Installation of free issue 900mm dia ducting
Connection of ducting into third party assets
Air testing of ducting
Backfilling

Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.
Quotations will be evaluated based on;
Cost
Timeliness of return
Adherence to and demonstration of understanding of the drawings and specifications provided at this point.
Provision of accurate product specifications to accompany the quotation.
Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.
Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail.
BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)
Acton Storm Tanks Worksite


More information

Links

Additional text

Acton Storm Tanks Worksite


About the buyer

Contact name

colin smith

Address

130 Wilton Road
London
SW1V1LQ
England

Telephone

07976181302

Email

colin.smith@tideway-west.london