Published date: 17 April 2024

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 29 April 2022, 12pm

Contract summary

Industry

  • Construction work - 45000000

Location of contract

England

Value of contract

£2,000,000 to £5,500,000

Procurement reference

KENT001-DN604754-78870992

Published date

17 April 2024

Closing date

29 April 2022

Closing time

12pm

Contract start date

8 January 2023

Contract end date

30 June 2024

Contract type

Works

Procedure type

Negotiated procedure

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Kent County Council (the Council) is the largest local authority in England covering an area of 3,500 square kilometres. It has an annual expenditure of over £1bn on goods and services and a population of 1.6m. The Council provides a wide range of personal and strategic services on behalf of its residents, operating in partnership with the NHS Kent and Medway Clinical Commissioning Group, 12 district councils, and 289 parish/town councils. KCC consists of four directorates:\r
\r
• Adult Social Care and Health;\r
• Children, Young People and Education;\r
• Growth, Environment and Transport; and\r
• Strategic and Corporate Services.\r
\r
This service is being commissioned on behalf of the Growth, Environment and Transport directorate.\r
\r
Scheme information\r
Due to their close geographic proximity, it is intended to procure the A20 Coldharbour Roundabout and Hall Road Junction schemes together as a single package.\r
\r
The A20 Coldharbour Roundabout scheme requires the design and construction of a new larger roundabout to replace the existing signal-controlled roundabout junction on the A20 at Coldharbour Lane. The junction connects the A20 corridor to the Strategic Road Network at Junction 5 of the M20. The site is located 2km to the north-west of Maidstone, Kent on the A20 corridor between Allington and Aylesford.\r
\r
The existing crossroad junction between the A20, Hall Road and Mills Road, approximately 500m to the west of the Coldharbour Roundabout, is to be improved by the design and construction of a lozenge shaped roundabout to replace the existing traffic signal-controlled junction. The Hall Road junction forms the only point of access to the busy Quarry Wood Industrial Estate and South Aylesford Retail Park.\r
\r
The intent of both schemes is to support the level and distribution of development being proposed in the Tonbridge and Malling Borough Council and Maidstone Borough Council Local Plans, with new home allocations of around 843 dwellings per annum (dpa) and 883 dpa respectively. Furthermore, the schemes aim to ease congestion along the A20 corridor in Aylesford.\r
\r
Suppliers should note and be aware that there is the possibility that the A20 Hall Road Junction Improvement may be withdrawn from the Contract, prior to the ITT being issued. In this situation the ITT will be issued for the A20 Coldharbour Roundabout only\r
\r
The construction cost budget for the A20 Coldharbour Roundabout scheme is £3.5m and for the Hall Road Junction scheme it is £2.0m


More information

Previous notice about this procurement

SC22080 - A20 Coldharbour Roundabout and Hall Road Junction

  • Opportunity
  • Published 30 March 2022

Links


Award information

Awarded date

4 January 2024

Contract start date

2 February 2024

Contract end date

30 December 2024

Total value of contract

£4,973,695.88

This contract was awarded to 1 supplier.

J Breheny Contractors Limited

Address

PE29 6EN

Reference

None

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Contact name

Craig Merchant

Address

County Hall
Maidstone
ME14 1XQ
England

Email

craig.merchant@kent.gov.uk

Website

http://www.kent.gov.uk