Published date: 26 July 2021
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Electrical equipment and apparatus - 31600000
Water installations - 39370000
Electrical wiring work - 45311100
Electrical installation work of transformers - 45317200
Electrical installation work of electrical distribution apparatus - 45317300
Electrical services - 71314100
Mechanical and electrical engineering services - 71334000
Location of contract
London
Value of contract
£501,000 to £1,000,000
Procurement reference
C4N56994212
Published date
26 July 2021
Closing date
11 August 2021
Closing time
12pm
Contract start date
19 January 2022
Contract end date
30 November 2029
Contract type
Works
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Temporary Electrics, Water and Site Services
WP39.1 scope consists of the design, supply, installation and site testing of all additional temporary electrics, water and other site services required during the constructions of the whole project which includes HS2 and GWML stations plus Shared Accommodation Building (SAB) at Old Oak Common Station.
All works to be as required during the construction and commissioning and comply fully with the Standards and Guidance documents, as identified in its section 5. Particularly HS2 standards and British Standards 7671:2018 and 7430 2011.
Scope of works will include:-
• Relocation of HV Transformers, Main Distribution Units (MDUs) and HV Cabling
• Control of switching for HV supplies
• Relocation of LV MDUs and cabling
• Installation of temporary lighting
• Relocation and supply of additional Road lighting
• Relocation and supply of additional 110V Transformers, cabling, and socket boxes
• Modify existing, supply and Installation of new MDUs
• Modification of existing, supply and Installation of new vehicle changing units
• Re-cabling tower cranes and plant power supplies and lightning suppression units as they are moved to suit the project programme
• Progressive removal of electrical installation at completion of the project
• Installation of additional vehicle and plant changing points
• Periodic electrical testing for BS7671 and PAT requirements
• Relocation, adjustment, and additional site 200mm and 80mm water mains, including values, chambers, and meters
• Relocation of Hydrant mains and Hydrants
• Modifications to site over pumping and power supplies
• Additional temporary fire mains within the construction project
• Installation of standpipes
• Disinfection of water pipework
• Modifications to site WIFI systems
• Modifications to site wide BMS electric and Water meter connections
• Changes to the site drainage systems
• Maintain and relocation of site ventilation system
• Relocation and powering of wheel wash and weight bridge
The subcontractor is to develop designs to include the installation processes, commissioning, testing and maintain a detailed set of drawings plus operation and maintenance manuals for the temporary installation.
Liaison with BBVS, WSP (main designers) and other Subcontractors will be required in the all works area.
Contract will be NEC3 ECC Option E
About the buyer's selection process:
Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.
The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.
What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: HSEQ, Commercial, Programme, Methodology (particularly with working in a track environment).
Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.
The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.
What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: Commercial, Programme, Methodology, HSEQ, Capability and Capacity.
In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Interchange at Old Oak Common.
No Documentation is included at this point.
More information
Links
-
- https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=56994259
- Tender notice
- Please follow this link to view the notice.
Additional text
-
No Documentation is included at this point.
About the buyer
Contact name
Manish Tailor
Address
Astral House Imperial Way
Watford
WD244WW
UK
Telephone
07738982498
Share this notice
Closing: 11 August 2021, 12pm