Published date: 3 November 2017
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Construction work - 45000000
Works for complete or part construction and civil engineering work - 45200000
Building construction work - 45210000
Construction work for buildings relating to law and order or emergency services and for military buildings - 45216000
Construction work for buildings relating to law and order or emergency services - 45216100
Construction work for buildings relating to law and order - 45216110
Police station construction work - 45216111
Engineering works and construction works - 45220000
Structures construction work - 45223000
Parking lot construction work - 45223300
Location of contract
OL16 1AG
Value of contract
£0 to £150,000
Procurement reference
20171103120020-35572
Published date
3 November 2017
Closing date
24 November 2017
Contract start date
15 January 2018
Contract end date
26 March 2018
Contract type
Works
Procedure type
Open procedure
Any interested supplier may submit a tender in response to an opportunity notice.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
The works comprise the necessary demolition, building, alteration and repair works associated with replacing the existing concrete ramp deck in order to improve the existing access and egress route from the upper deck of the existing car park, as identified on the site plan.
Whilst undertaking the role of Principal Contractor the successful building contractor will liaise and manage all relevant subcontractors in order to complete the works as identified within the Schedule of Works.
The Contractor must visit the site and satisfy themselves as to working conditions including facilities and restrictions for access, storage of materials, etc; and risk of injury or damage to persons and property. No claim for extras will be entertained on the grounds that the Contractor did not or could not foresee any matter that may in fact affect or have affected the execution of the works.
Full details of the required works, including plans, diagrams and photographs are available by downloading the Invitation to Tender document, via the Bluelight e-tendering portal.
It is expected that work will begin in mid-January 2018 and the contract will last until completion of the works (estimated at 10 weeks).
More information
Links
-
- https://uk.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=21990&B=BLUELIGHT
- Tender notice
- Additional data
-
- https://uk.eu-supply.com/ctm/Company/CompanyInformation/Index/35572
- Tender notice
- User / Company
About the buyer
Contact name
Ali Cordrey
Address
Greater Manchester Police
Openshaw Complex, Lawton Street
Manchester
M11 2NS
ENG
Telephone
+44 1618561333
Share this notice
Closing: 24 November 2017
All content is available under the