Published date: 21 October 2022

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 28 October 2022, 12pm

Contract summary

Industry

  • Ground-stabilisation work - 45111230

Location of contract

North East, North West, Yorkshire and the Humber

Value of contract

£300,000 to £500,000

Procurement reference

SMP Alliance - M62 Compound Soil Stabilisation

Published date

21 October 2022

Closing date

28 October 2022

Closing time

12pm

Contract start date

12 December 2022

Contract end date

28 April 2023

Contract type

Works

Procedure type

Competitive quotation (below threshold)

The buyer selects a group of potential suppliers to invite to tender.

This procedure can be used for procurements below the relevant contract value threshold.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

Yes


Private procurement rules

Supply chain notices are business-to-business transactions and are not bound by the same rules and restrictions as public sector contracts. The UK government is not responsible for the conduct of such procurement.


Description

The Smart Motorways Programme (SMP) Alliance: The smart motorway programme seeks to further increase the safety performance of National Highways' strategic road network and mitigate capacity constraints to enhance our customer experience. National Highways have brought together six partners to act with them in an alliance across three functions to deliver the 10yr programme:
Production Hub: Fluor Ltd
• Digitally Enabled Design Partners: Jacobs UK Ltd and WSP UK Ltd
• On-Site Assembly Partners (OSAPs): bmJV (a joint venture between BAM Nuttall Ltd and Morgan Sindall Construction & Infrastructure Ltd), Balfour Beatty Civil Engineering Ltd and Costain Ltd

Scope

On behalf of the SMP Alliance Partners (The Contracting Authority) noted above, we are now inviting expressions of interest for the provision of soil stabilisation works to an area of c.20,000m2 of the M62 J19 compound.
To register your interest in this opportunity please email: andrew.taperek@costain.com
The SMP Alliance reserves the right to short list those registered.
To register for this opportunity please provide Constructionline accreditation.


About the buyer

Contact name

Andrew Taperek

Address

Birmingham
Birmingham
B4 6BN
England

Email

andrew.taperek@costain.com