Published date: 2 August 2024

Last edited date: 2 August 2024

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 6 December 2023, 12pm

Contract summary

Industry

  • Construction work - 45000000

Location of contract

NR4 7TJ

Value of contract

£0 to £87,983,160.82

Procurement reference

IT-37-845-PURCON2023 - AWARD

Published date

2 August 2024

Closing date

6 December 2023

Closing time

12pm

Contract start date

24 July 2024

Contract end date

14 January 2027

Contract type

Works

Procedure type

Other

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

The University of East Anglia was created during the 1960s. Its original campus buildings were designed by the acclaimed architect Sir Denys Lasdun and several of the original buildings are now Grade II Listed, including the original teaching and science building the Lasdun Wall. The Grade II listed Lasdun Wall is an iconic and important part of University of East Anglia's (UEA) history situated in the centre of the UEA's vibrant and busy 24/7 campus. However, the building needs repair and refurbishment to address condition issues and to deliver essential sustainability improvements to enable the University to meet their target to be a net zero campus by 2045. The Lasdun Wall comprises four buildings constructed to appear as one (Building 3, Building 4, Building 5 and Building 6). The University plans to carry out a four-phase strip-back-to-frame refurbishment of the Lasdun Wall. This project - Lasdun Wall Refurbishment Phase 1 - will deliver new modern science facilities and teaching space in an extended Building 3, whilst existing science research facilities continue to operate within Buildings 4, 5 and 6. The existing science facilities are currently at risk due to potential condition failures of the buildings, therefore the success of Phase 1 to 'de-risk' highly specialised facilities within the Lasdun wall, is of extreme importance to the University.

The University's Phase 1 project consists of three elements

Preliminary enabling works (by others)
The Main Works (the subject of this procurement)
A package of interphase enabling works which will complete Phase 1 and prepare for the future decommissioning of Buildings

The appointed Main Contractor will be required to undertake the following:

Initial phase of strip out and asbestos removal will have been undertaken to provide an empty shell, however asbestos removal will be required by the main contractor as follows:

Facades - Around existing windows which will be replaced, and concrete façade panels removed to accommodate the new extension.
Existing floor screed abutting the perimeter which includes asbestos contamination around existing fixings to the retained listed concrete façade panels - fixings and all remaining screeds will need to be removed.
Within the tender design information, we have included the Asbestos survey report to support with the remaining asbestos removal, sequencing and overall methodology. All Asbestos must be removed.

Extension - An extension of approx. 2,966m² is planned to one elevation.

Window Replacement and Façade Treatment - The building is listed and the facades are a sensitive architectural feature which will need to be carefully replaced with modern windows in similar style.

Fitting Out of existing building - The re-fit comprises circa 11,287m² of space split to include science research facilities and teaching and social learning space.

External Works as detailed in the ISIT design i...


Award information

Awarded date

24 July 2024

Contract start date

24 July 2024

Contract end date

14 January 2027

Total value of contract

£87,983,160.82

This contract was awarded to 1 supplier.

Mace

Address

155 Moorgate, London, United Kingdom, EC2M 6XB

Reference

None


About the buyer

Contact name

Claire Woodcroft

Address

University of East Anglia
Norwich Research Park
Norwich
NR4 7TJ
United Kingdom

Telephone

01603 592728

Email

c.woodcroft@uea.ac.uk