Published date: 8 June 2022

This notice was replaced on 9 September 2022

This notice does not contain the most up-to-date information about this procurement. The most recent notice is:

Opportunity (published 9 September 2022)

Closed future opportunity - This means that a potential contract has passed its approach to market date. A buyer can choose to consider any supplier interest or convert this notice into an opportunity ready for live procurement.


Contract summary

Industry

  • Construction work for college buildings - 45214300

Location of contract

MK6 5LP

Value of contract

£5,011,966

Procurement reference

MKC - Refurb

Published date

8 June 2022

Approach to market date

5 September 2022

Contract start date

23 January 2023

Contract end date

30 September 2024

Procedure type

Open procedure (above threshold)

Any interested supplier may submit a tender in response to an opportunity notice.

This procedure can be used for procurements above the relevant contract value threshold.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Program - Works to be carried out between 23 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].

The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:

Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]

Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.

Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];

Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.

Tender period - First Stage Tender - 05 Sept 2022 - 07 October 2022 [5 weeks]

Adjudication & contractor interviews - 10 - 21 October 2022 [2 weeks]

Second Stage Tender - 24 October 2022 - 02 December 2022. [6 weeks]

Adjudication & contractor appointment - 05 December - 23 December 2022.

Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON

Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest


More information

Spend profile

This table displays the spend profile of the notice
Financial year Budget
2022/2023 £1,500,000
2023/2024 £3,511,966

About the buyer

Contact name

Craig Pullen

Address

Milton Keynes College
Milton Keynes
MK6 5LP
England

Telephone

07531975978

Email

craig@cpconsulting.org.uk