Industry
Construction work for college buildings - 45214300
Location of contract
MK6 5LP
Value of contract
£5,011,966
Procurement reference
MKC - Refurb
Published date
8 June 2022
Approach to market date
5 September 2022
Contract start date
23 January 2023
Contract end date
30 September 2024
Procedure type
Open procedure (above threshold)
Any interested supplier may submit a tender in response to an opportunity notice.
This procedure can be used for procurements above the relevant contract value threshold.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Program - Works to be carried out between 23 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].
The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:
Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]
Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.
Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];
Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - First Stage Tender - 05 Sept 2022 - 07 October 2022 [5 weeks]
Adjudication & contractor interviews - 10 - 21 October 2022 [2 weeks]
Second Stage Tender - 24 October 2022 - 02 December 2022. [6 weeks]
Adjudication & contractor appointment - 05 December - 23 December 2022.
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest
More information
Spend profile
Financial year | Budget |
---|---|
2022/2023 | £1,500,000 |
2023/2024 | £3,511,966 |
About the buyer
Contact name
Craig Pullen
Address
Milton Keynes College
Milton Keynes
MK6 5LP
England
Telephone
07531975978
Share this notice