Published date: 19 November 2025

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 29 June 2025, 3pm

Contract summary

Industry

  • Surface work for highways - 45233210

Location of contract

East Midlands, West Midlands

Value of contract

£167,882.45

Procurement reference

tender_512503/1533295

Published date

19 November 2025

Closing date

29 June 2025

Closing time

3pm

Contract start date

30 June 2025

Contract end date

13 November 2025

Contract type

Works

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Background Information for the proposed Work Order

A46 Guys Cliffe IC contains two under bridges that carry the dual carriageway Warwick bypass over the interchange link roads with the A429 and B4115. The two bridges are single span simply supported structures with composite decks comprised of pre-stressed beams and 200mm thick slabs cast upon permanent formwork between beams. The end supports are reinforced concrete cantilever abutments, which are constructed in two
sections and separated by a movement joint at the centre line. Each abutment is flanked by reinforced concrete tapered wing walls. The deck is free to move at the south end and fixed at the north end

In November 2003, secondary Open Box Beam (OBB) Vehicle Restraint Systems (VRS) were installed on both sides of both structures to protect the existing substandard BACO Aluminum parapets (P1 System). The OBB barrier is flared back and connected into the Tensioned Corrugated Beams (TCB) barrier apart from ramped OBB barrier on the departure end of the South Bridge. This secondary OBB has substandard set-back and working width.

The bridge records indicate that both bridges were re-waterproofed in 1993 by Acrylic and Polyurethane spray over the entire deck and again in 2003 with spray applied system at the verges only (on top of new C50 verge
concrete) in conjunction with parapet protection works (OBB barrier installation). This is based on the 2003 Contract Drawing contained within IAMIS (S.22.002/A) and service life can be considered for minimum 35
years.

The existing deck waterproofing at the North Bridge was damaged on both the northbound and southbound carriageways during a resurfacing intervention in 2013. The waterproofing remains in its damaged state. Following the option study undertaken by Kier to address the damaged waterproofing at the north bridge and the substandard secondary protection at both bridges, an addendum to the Options report was submitted.

The addendum VRS replacement option on both bridges is to replace the VRS with new N2 W1 metal VRS and to replace the current verge with a new reinforced concrete plinth with cast-in cradles to form a fixing for the VRS and resin anchoring steel 'U' bars into the bridge deck. For the North Bridge, waterproofing will be sprayed from the new plinth, under the kerb, across the carriageway, and shall form a joint with the existing central reserve waterproofing in the channel fronting the kerb.

For the South Bridge, waterproofing will be sprayed from the new plinth, under the kerb, and shall form a joint with the existing carriageway waterproofing in the channel
fronting the kerb. A departure from standards has been approved for the new VRS to have reduced setbacks. An asbestos survey and adhesion testing of


Award information

Awarded date

28 March 2025

Contract start date

30 June 2025

Contract end date

13 November 2025

Total value of contract

£167,882.45

This contract was awarded to 1 supplier.

EUROVIA INFRASTRUCTURE LIMITED

Address

Albion House, Springfield Road, Horsham, West Sussex, RH12 2RW

Reference

Companies House number: 07388667

Supplier is SME?

No

Supplier is VCSE?

No