Published date: 24 June 2024
Last edited date: 4 July 2024
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Demolition, site preparation and clearance work - 45111000
Construction work for houses - 45211100
Location of contract
West Midlands
Value of contract
£1,000,000 to £5,000,000
Procurement reference
BIP870179406
Published date
24 June 2024
Closing date
2 August 2024
Closing time
12pm
Contract start date
1 March 2025
Contract end date
1 April 2026
Contract type
Works
Procedure type
Open procedure
Any interested supplier may submit a tender in response to an opportunity notice.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
NOTE: This notice was updated on 04 July 2024 for the following reason: Tender return deadline has been extended to 16 August 2024 (12:00)(The demolition of existing dwellings and the design and construction of 12Nr 1B2P flats, 14Nr 2B3P houses and 6Nr 3B5P houses, together with all external works and services at Fairfields Close, Gobowen.
Target Date for Electrical Diversion Works to be ordered through SPEN: October 24
Target Start for construction works: March 25
Target completion date: April 26
Tender Return Deadline: 12 Noon 2 August 2024)
More information
Links
-
- https://www.delta-esourcing.com/tenders/UK-GB-Shrewsbury:-ST&R-010---New-Build-at-Fairfield-Close,-Gobowen,-Shropshire/88P42733XJ
- Please follow this link to view the notice.
Additional text
-
The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
Please note the tender return deadline is 12:00 2 August 2024.
Contractor's will be required to carry out a relocation of an existing substation on the site before the construction works can commence. All works to be managed by the contractor and carried out in accordance with SPEN requirements. The first priority on the project will be to liaise with SPEN to get this element of works booked in.
See page 7 of the Employer's Requirements for further specific items relating to the project.
About the buyer
Contact name
Procurement team
Address
Shirehall
Shrewsbury
SY2 6ND
UK
Telephone
+441743252993
Share this notice
Closing: 2 August 2024, 12pm