Published date: 5 June 2023

Last edited date: 6 June 2023

Closed early engagement


Closing date: 23 June 2023

Contract summary

Industry

  • Construction structures and materials; auxiliary products to construction (except electric apparatus) - 44000000

  • Construction work - 45000000

Location of contract

East of England

Procurement reference

S500 - Drainage

Published date

5 June 2023

Closing date

23 June 2023

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

Yes


Description

NOTIFICATION OF SUBCONTRACT PACKAGE

A47 North Tuddenham to Easton Scheme

Package: Drainage

Galliford Try, as the East Region Delivery Partner are delivering the A47 Tuddenham to Easton Dualling project in the county of Norfolk on behalf of Highways England.

The project will complete the dual carriageway between Norwich and Dereham, supporting economic growth and easing congestion in the area.

The project has recently submitted a Development Consent Order to the Planning Inspectorate and the project is forecast to commence on site in early 2024 and will take around 2 years to complete.

The A47 Tuddenham to Easton delivery team is looking for Contractors to deliver the drainage works.
The works include but not limited to Filter Drains, Carrier Drain and all associated chambers, catchpits, etc.

Outline Scope of Works - The Package of Drainage consists:

- Excavation of trenches and install drainage pipes, ensuring proper alignment, gradients, and connection points.
- Construction of gullies, manholes, and catchpits at appropriate intervals and depths according to the design specifications.
Installation of filter and carrier pipes, as well as any necessary drainage accessories.
- Backfilling the excavated trenches with suitable materials, ensuring proper compaction to achieve desired stability and surface level.
- Reinstatement the surrounding areas, such as pavements, roadways, and verges, to their original condition.

Principal Approximated Quantities:
Narrow Filter Drains: 4,233 lm
Ditches: 16,344 lm
Combined drainage and kerb blocks: 6,756 lm
Drains and Service Ducts: 17,024 lm
Filter Drains: 31,474 lm
Chambers and Gullies: 1,085 no.
Headwalls and Outfall Works: 95 no.

All interested contractors should hold all the relevant certification and qualifications for providing these type of works

Programme:
It is anticipated that the drainage will commence early 2024

Timings:
Deadline for Notifications of Interest 16:00 hrs on 23rd June 2023

Galliford Try Procurement Process:
To secure work with Galliford Try, a supplier will need to pass the PAS91 onboarding process administered through Builders Profile. Details will be shared with shortlisted Subcontractors.

If this package is of interest to your Company, please contact our procurement team by e-mail via the following email address:
HE019-A47TUD-EXP@4projectsmail.com

by the above deadline with your notification of interest and details of your capabilities.

Any notifications of interest after the above deadline will not receive a response.


About the buyer

Contact name

Bruno Ribeiro

Address

Po Box 17452,2 Lochside View
EDINBURGH
EH121LB
Scotland

Telephone

0121 717 5400

Email

HE019-A47TUD-EXP@4projectsmail.com