Published date: 20 October 2023

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 10 November 2023, 12pm

Contract summary

Industry

  • Construction work - 45000000

  • Repair and maintenance services - 50000000

  • Architectural, construction, engineering and inspection services - 71000000

Location of contract

England

Value of contract

£40,000

Procurement reference

WIGN001-DN695374-70698664

Published date

20 October 2023

Closing date

10 November 2023

Closing time

12pm

Contract start date

4 December 2023

Contract end date

17 December 2023

Contract type

Works

Procedure type

Open procedure

Any interested supplier may submit a tender in response to an opportunity notice.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

The works briefly comprise:
• Saw cut and break out carriageway, footway/verge to reveal existing waterproofing and buried joint.
• Works to be carried out in phases to minimise traffic disruption.
• Remove existing joint and Prepare surface to receive a new Thormajoint BJ 200ST Type 2 Asphalt Plug Joint.
• Install new Thormajoint BJ 200ST Type 2 Asphalt Plug Joint, to include a skid resistant dressing stone 1.4-2mm.
• Reinstate carriageway, footway/verge and any affected road markings.
• Remove existing polysulphide sealant to bridge edge beams and replace with new polysulphide sealant.
• Due to the location, the works will need to be carried out between 19:00 - 07:00


About the buyer

Contact name

Christopher Dunn

Address

Wigan Council
PO Box 100
Wigan
WN1 3DS
England

Telephone

+44 1942489272

Email

christopher.dunn@wigan.gov.uk

Website

http://www.wigan.gov.uk/