Published date: 21 May 2024

Last edited date: 18 December 2024

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 25 March 2024, 5pm

Contract summary

Industry

  • Installation of fitted kitchens - 45421151

Location of contract

East of England

Value of contract

£2,945,000

Procurement reference

NRW/21041

Published date

21 May 2024

Closing date

25 March 2024

Closing time

5pm

Contract start date

1 April 2024

Contract end date

31 March 2026

Contract type

Works

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

*UPDATED 16/08/2024 AND 18/12/2024 - SEE VARIATION INFORMATION UNDER SUPPLIER AWARD DETAILS*

Contract to undertake kitchen installation works to council owned dwellings as per works programme. A Direct Award has been made via a call-off from a Framework with Eastern Procurement Limited (EPL).

EPL is a not-for-profit organisation offering specialist compliant framework agreements, social landlords and other public sector bodies, predominantly in the Eastern region. The council are owner members of EPL and work closely with them to create bespoke procurement frameworks. The frameworks promote value for money for the council and include SMEs and local suppliers.


Award information

Awarded date

28 March 2024

Contract start date

1 April 2024

Contract end date

31 March 2026

Total value of contract

£2,945,000

This contract was awarded to 1 supplier.

Gasway Services Limited

Address

18 Burnet Road
Sweet Briar Road
Industrial Estate
NORWICH
NR3 2BS

Reference

Companies House number: 04158628

Value of contract

£2,945,000

Supplier is SME?

Yes

Supplier is VCSE?

No

Additional details

Original award was made 28/03/2024 for value of £499,000 from 01 April 2024 to 31 March 2025.

As no Cabinet meeting was held in June 2024 due to the General Election, an Urgent Decision was made for a variation to the contract. The Chief Executive of Norwich City Council took this decision following consultation with the Leader of the Council, leaders of all political groups, chair of Scrutiny Committee, the Portfolio Holder for Housing, Monitoring Officer and the Chief Finance Officer.

Jul24 - The contract has been varied for the period to 30 June 2025 with an increased awarded contract value of £957,749.00.

On 13/11/2024 - a meeting of Cabinet was held. It was noted the dates of the initial contract period should be 01/04/2024 to 31/03/2025 as originally awarded 28/03/2024 (the date up to 30/06/2025 as varied in July24 was incorrect). It was approved that an additional value of £270,000 was needed to be able to complete the works programme to 31/03/2025. In addition, the optional extension option from 01/04/2025 to 31/03/2026 was approved at a value of £1,515,000. Contract total for full 2 years of £2,945,000.00. As awarded under a Framework, the full procurement exercise is fully compliant with PCR 2015.


About the buyer

Address

City Hall
St Peters Street
NORWICH
NR21NH
England

Email

procurement@norwich.gov.uk