Published date: 22 February 2019

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 1 March 2019

Contract summary

Industry

  • Footpath construction work - 45233161

  • Surface work for footpaths - 45233253

  • Foundation work for highways, roads, streets and footpaths - 45233300

    • Foundation work for footpaths - 45233340

Location of contract

South East

Value of contract

£100,000

Procurement reference

EPSEWL001-DN394761-48332702

Published date

22 February 2019

Closing date

1 March 2019

Contract start date

1 July 2019

Contract end date

31 December 2019

Contract type

Works

Procedure type

Restricted procedure

A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

Yes


Description

The project consists of the reconstruction/restoration of footpaths on Horton Country
Park belonging to Epsom and Ewell Borough Council. Over the years the existing
ride surfaces have degraded. The surface of the rides are covered with a variety of
lime scalping's or crushed asphalt.
We refer to drawing Horton-001, which should be read in conjunction with the
Schedule of Works. The drawing annotates three paths, coloured coded in Magenta,
Brown and Green which are all to be included for restoration.
Horton Country Park is a Local Nature Reserve and all the paths to be restored are
public bridleways where diversions will be in operation. Therefore all work and
vehicle movements must be carried out with due care to the grounds and also to the
public using them, adhering to the requirement of the Natural England consent for
the works. The site is accessed from Horton Country Park car park off Horton Lane,
Epsom, (51°20'36.4"N 0°17'27.5"W). There are various possible locations within the
site for a compound(s) and for the storing of surfacing materials. All materials are to
be stored in a designated area within the compound(s) and then transported to the
work area by means of a dumper.
Following the Works, the Contractor should also allow for repair and making good of
the area used for storage of path surfacing and plant.


About the buyer

Contact name

Bhavesh Amin

Address

Town Hall
The Parade
Epsom
KT18 5BY
United Kingdom

Telephone

+44 1372732235

Email

BAmin2@epsom-ewell.gov.uk