Published date: 1 July 2024
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork - 45230000
Location of contract
South East
Value of contract
£168,171.12
Procurement reference
UN23503
Published date
1 July 2024
Closing date
13 December 2023
Closing time
2pm
Contract start date
5 February 2024
Contract end date
18 March 2024
Contract type
Works
Procedure type
Call-off from a framework agreement
A mini-competition or direct purchase from a pre-established framework agreement.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
A call-off from the Generation 4-ONE 2020 - 2024 Civil Engineering, Highways and Transportation Collaborative Framework (Awarded April 2020).
Installation of a new temporary controlled crossing with priority change at junction by making Clifton Terrace one way. The works comprise of the provision of new bollards, cycle infrastructure, kerbing, signage and road markings and the installation of traffic signal infrastructure needed for the new crossing. Construction of the first phase shall be completed in 6 weeks and will be maintained by the Contractor for a period of 9 months.
Award information
Awarded date
3 January 2024
Contract start date
5 February 2024
Contract end date
18 March 2024
Total value of contract
£168,171.12
This contract was awarded to 1 supplier.
Rocon Contractors Limited
Address
Vyne Lodge Farm, Vyne Road, Bramley, Tadley, Hampshire, RG26 5DX
Reference
Companies House number: 00732319
Value of contract
£168,171.12
Supplier is SME?
Yes
Supplier is VCSE?
No
Share this notice
Closing: 13 December 2023, 2pm