Published date: 27 May 2021
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Construction structures and materials; auxiliary products to construction (except electric apparatus) - 44000000
Construction work - 45000000
Location of contract
East of England, South East
Value of contract
£1
Procurement reference
A47 Blofield to North Burlingham Dualling - ECI Earthworks
Published date
27 May 2021
Closing date
4 June 2021
Closing time
4pm
Contract start date
2 August 2021
Contract end date
31 March 2023
Contract type
Works
Procedure type
Competitive procedure with negotiation (above threshold)
Anyone may ask to participate, but only those who are pre-selected will be invited to submit initial tenders and to negotiate.
This procedure can be used for procurements above the relevant contract value threshold.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
A47 Blofield to North Burlingham Dualling
Galliford Try, as the East Region Delivery Partner are delivering the A47 Blofield to North Burlingham Dualling project in the county of Norfolk on behalf of Highways England. The project will replace the existing single-lane section of the A47 between Blofield and North Burlingham with a new two-lane dual carriageway 70m south of the existing road and include safety improvements existing junctions.
The project has recently submitted a Development Consent Order to the Planning Inspectorate and the project is forecast to commence on site in late 2022 and will take around 1.5 years to complete.
Package: Earthworks
Outline Scope of Works
The Earthworks Package consists of two parts:
Stage 1: Early Contractor Involvement. To provide technical and commercial input into the detailed design phase and to formulate the budget and programme for the works.
Stage 2: Construction. To provide all necessary supervision, labour, plant and materials required to undertake the earthworks comprising the excavation, processing, placement and compaction of site won soils and the Import of suitable fill material to form the development platform to support the new road, structures and landscaping. The contractor will also be responsible for the disposal to stockpile or off site of any unacceptable or surplus soils and other materials generated during the bulk earthworks.
Principal Activities Approximate Quantities
Excavation of class 5a 74,000m3
Excavation excluding class 5a 109,000m3
Imported Fill 205,000m3
Deposition of fill 54,000m3
Compaction of Fill 205,000m3
Programme
It is currently anticipated that the Stage 1 ECI works will commence in August 2021.
Timings
Deadline for Notifications of Interest 16:00 hrs on Friday 4th June 2021
Galliford Try procurement process
To secure work with Galliford Try, a supplier will need to pass the PAS91 onboarding process administered through Builders Profile. Details will be shared with shortlisted suppliers.
If this package is of interest to your company please contact our procurement team by e-mail via the following email address: Tender.returns@4projectsmail.com, by the above deadline with your notification of interest and details of your capabilities.
Any notifications of interest after the above deadline will not be responded to.
Share this notice
Closing: 4 June 2021, 4pm