Published date: 2 July 2020
This notice was replaced on 4 April 2022
This notice does not contain the most up-to-date information about this procurement. The most recent notice is:
Awarded contract (published 4 April 2022)
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Construction work - 45000000
Construction work for highways, roads - 45233100
Road-repair works - 45233142
Surface work for highways - 45233210
Resurfacing works - 45233251
Engineering design services - 71320000
Location of contract
South East
Value of contract
£120,000,000 to £160,000,000
Procurement reference
KENT001-DN484494-89269450
Published date
2 July 2020
Closing date
3 August 2020
Contract start date
1 January 2021
Contract end date
31 December 2022
Contract type
Works
Procedure type
Negotiated procedure
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Kent County Council (the Authority) is the largest local authority in England covering an area of 3 500 km2. It has an annual expenditure of over GBP 1 billion on goods and services and a population of 1.5 million. the client provides a wide range of personal and strategic services on behalf of its residents, operating in partnership with 12 district councils and 309 parish/town councils.
The Authority consists of three operational directorates (Adult Social Care and Health, Children, Young People and Education and Growth, Environment and Transport) and one service directorate (Strategic and Corporate Services). This requirement is for the Road and Footway Asset Team who are responsible for maintaining and managing the structural and surface condition of our roads, footways and cycle tracks.
To effectively maintain our roads, footways and cycle tracks we undertake the delivery of renewal works to replace deteriorated areas which have reached the end of their useful life and preservation works to prolong the life of areas which are starting to deteriorate.
The scope of work at each site will generally entail the cold milling of the top layers of the road structure and repaving with an asphalt surface and/or binder course. All sites will include adjustments to covers and replacement of road markings and road studs where required.
Sites approaching traffic signals may require the replacement of the traffic loops. It is anticipated that many sites will require road closures and night-time working with working restrictions in place with defined times.
The project consists of multiple sites. There will be several phases of work throughout the contract period, with routine work carried out between January and November each year. The initial phases are planned as follows, subject to weather conditions:
•Phase 1 - January to March 2021
•Phase 2 - April to November 2021
•Phase 3 - January to March 2022
•Phase 4 - April to November 2022
The new contract will commence upon 1st January 2021 and will continue for a period of 24 months unless terminated in accordance with the Conditions of Contract.
More information
About the buyer
Contact name
Robert Clark
Address
Invicta House
Maidstone
ME14 1XX
England
Telephone
+44 3000415951
Website
Share this notice