Contract summary

Industry

  • Electrical installation work - 45310000

  • Heating, ventilation and air-conditioning installation work - 45331000

Location of contract

South East

Value of contract

£1,198,951.91

Procurement reference

CDC - 033703

Published date

4 April 2022

Closing date

22 February 2022

Closing time

12pm

Contract start date

9 March 2022

Contract end date

11 January 2023

Contract type

Works

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

Chichester District Council (CDC) has appointed a lead contractor for the decarbonisation of Westgate leisure centre, as part of a Direct award call-off from Portsmouth City Council's 'Combined Heat & Power Engine - Multi Contractor Framework Agreement'. Chichester District Council received a £1.35m grant from the Public Sector Decarbonisation Scheme for the installation of decarbonisation technologies at Westgate Leisure Centre, Chichester. The leisure centre includes a swimming pool, fitness gym, exercise studios, 6 court sports hall, health suite and café. It has a total useful floor area of 6,400 sq. m. It was constructed in the 1980s and the health suite was added in 1999. The centre is run by tenant Everyone Active.

Chichester District Council is implementing a number of renewable energy technologies and energy efficiency measures to decarbonise and reduce the site's reliance on fossil fuels. These technologies and measures include: rooftop solar PV, rooftop solar thermal, air source heat pump (ASHP), CHP (Combined Heat & Power) unit optimisation, energy monitoring equipment and software, and an administrative request to the Distribution Network Operator.

The proposed system will deliver:

1. The annual financial savings of the project from energy savings must be 120% or greater than the total annual O&M costs
2. The measures used to reduce these emissions in aggregate do not exceed a cost of £500 / tCO2e LT saved.
3. The project must be delivered on budget (as proposed by the supplier)
4. Any defects must be addressed within 6 months of practical completion


Award information

Awarded date

9 March 2022

Contract start date

9 March 2022

Contract end date

11 January 2023

Total value of contract

£1,198,951.91

This contract was awarded to 1 supplier.

Veolia CHP UK Ltd

Address

210 Pentonville Road, London, N1 9JY

Reference

Companies House number: 02670549

Value of contract

£1,198,951.91

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Address

1 East Pallant
CHICHESTER
PO191TY
England

Telephone

01243 785 166

Email

asmith@chichester.gov.uk