Published date: 21 June 2022
Last edited date: 22 June 2022
Closed early engagement
Contract summary
Industry
Construction structures and materials; auxiliary products to construction (except electric apparatus) - 44000000
Construction work - 45000000
Location of contract
East of England
Procurement reference
S100-Traffic Management
Published date
21 June 2022
Closing date
4 July 2022
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
Yes
Description
NOTIFICATION OF SUBCONTRACT PACKAGE
A47 Blofield to North Burlingham Dualling
Temporary Traffic Management
Galliford Try, as the East Region Delivery Partner are delivering the A47 Blofield to North Burlingham Dualling project in the county of Norfolk on behalf of National Highways.
The project will replace the existing single-lane section of the A47 between Blofield and North Burlingham with a new two-lane dual carriageway 70m South of the existing road length and is 5km in length including safety improvements to the existing junctions.
The project total cost is estimated to be in the region of £100million pounds plus.
Outline Scope of Works
Setting up and demobilising Temporary Traffic Management equipment including Maintaining equipment as listed below: -
Boundary fence - 13th Oct - 9th Nov 22
Enabling Works - Setting out, Welfare & Site clearance 02nd Nov 22 - 08th Nov 22
Set up compound and Welfare 23rd Nov-22 - 28th Feb23
Site clearance for utilities 09th Jan 23 - 20th Jan23
Vegetation & site clearance 09th Jan 23 - 20th Jan 23 & 19th Oct 22-26th Oct 22 & 23rd Jan 23 - 27th Jan 23
Satellite compounds 23rd Jan 23 - 03rd Mar 23
Access track to S01 06th Mar 23 - 10th Mar-23 & 13th Mar-23 - 17th Mar-23
Temp.welfare 13th Oct-22-18th Oct-22
Access Points on Byroads 20th Oct 22 - 31st Oct-22
West Compound Topsoil Strip & Stone 24th Oct 22 - 25th Oct-22 26th Oct 22 - 01st Nov 22
AW01 Diversion 27th Oct 22 - 02nd Nov 22
Allotment Carpark Relocation 02nd Nov-22 - 08th Nov-22
Access Track to East Compound 09th Nov-22 - 11th Nov-22 & 23rd Nov 22 -25th Nov-22
Relocate Water Tower 09th Nov 22 - 11th Nov 22
East Compound Topsoil Strip & Stone 14th Nov 22 -15th Nov 22 & 16th Nov 22 - 22nd Nov-22
TM 1 - Offline 23rd Nov 22 - 08th May 23
TM 2 - Offline 09th May-23 - 22nd Aug 23
TM 5 - weekend overnight - Cross-over 09th-May-23 - 23rd Aug 23
TM 3 - Offline works 23rd Aug-23 -18th-Oct 23
TM 5 - Weekend/Overnight closures - tie-in for Phase 4 28th Sep 23 -18th Oct 23
TM 4 - TM Switch at CH 3300 19th Oct-23 - 14th May 24
TM 5 - Weekend/Overnight closures tie-in for Phase 6 10th May 24 - 10thMay 24
TM 6 - Using new WB alignment 15.May 24 - 28.Jun 24
TM 7 - Lane 1/1 Finishing works 01.Jul 24 - 22.Aug 24
The estimated contract amount for this package is expected to be over £1,000,000
Programme
It is anticipated that the Temporary Traffic Management works will commence during Early October 2022
Galliford Try Procurement Process
To secure work with Galliford Try, a supplier will need to pass the PAS91 onboarding process administered through Builders Profile. Details will be shared with shortlisted Subcontractors.
If this package is of interest to your Company, please contact our procurement team by e-mail via the following email address: GTA47BLOSupplier.EOI@4projectsmail.com by the above deadline with your notification of interest and details of your capabilities.
Any notifications of interest after the above deadline will not receive a response.
About the buyer
Contact name
Bruno Ribeiro
Address
Po Box 17452,2 Lochside View
EDINBURGH
EH121LB
Scotland
Telephone
0121 717 5400
Share this notice
Closing date: 4 July 2022