Published date: 4 September 2017
Last edited date: 4 September 2017
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Site preparation work - 45100000
Building demolition and wrecking work and earthmoving work - 45110000
Demolition, site preparation and clearance work - 45111000
Demolition work - 45111100
Location of contract
Yorkshire and the Humber
Value of contract
£325,000
Procurement reference
SHEFCC001-DN275408-87898327
Published date
4 September 2017
Closing date
12 June 2017
Contract start date
28 August 2017
Contract end date
28 August 2019
Contract type
Works
Procedure type
Restricted procedure
A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
The Works comprise a stand-by term Contract for emergency work and making safe or associated work to any property, building or structure 24 hours a day, 365 days a year including demolition of structures, strutting, propping, shoring, structural scaffolding, boarding up openings, Heras fencing, site accommodation, site based security, making good surfaces and structures and associated work. The Works will be carried out piecemeal under Orders issued by the Contract Administrator. Certain work in this category will be carried out by the Council's Repairs and Maintenance Service and / or Amey (if the Works impact upon the Highway Project Network) and, as such, this Contract will partly be a stand-by service in the event of the Council's Repairs and Maintenance Service and / or Amey not being able to undertake the preparatory work of boarding up and / or fencing. Properties and adjacent properties may be occupied during the progress of the Works. Emergency work requirements will be handed to the Contractor, either written or orally, based on an Order for each separate occurrence. The scope of work will vary greatly depending on the characteristics of each particular site or nature of the incident. Upon receipt of an Order the Contractor shall within 2 hours attend site, and if safe to do so, commence the work described on the Order. No continuity of work can be guaranteed. The Contractor shall allow in his rates for any additional costs in relation to out-of-sequence or uneconomical working methods and disruption due to the aforementioned criteria.
Award information
Awarded date
4 September 2017
Contract start date
2 October 2017
Contract end date
28 August 2019
Total value of contract
£332,688
This contract was awarded to 1 supplier.
MHH Contracting
Address
S9 4PS
Reference
None
Supplier is SME?
Yes
Supplier is VCSE?
No
About the buyer
Contact name
Lisa Oxley
Address
Capital Delivery Service
Level 3, East Wing, Moorfoot
Sheffield
S1 4PL
United Kingdom
Telephone
+44 1142736215
Website
Share this notice
Closing: 12 June 2017