Published date: 6 December 2019

This notice was replaced on 21 October 2020

This notice does not contain the most up-to-date information about this procurement. The most recent notice is:

Awarded contract (published 21 October 2020)

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Contract summary

Industry

  • Instrumentation and control equipment - 31682210

Location of contract

London

Value of contract

£2,600,000 to £5,000,000

Procurement reference

C4N47058547

Published date

6 December 2019

Closing date

20 December 2019

Contract start date

2 April 2020

Contract end date

10 July 2026

Contract type

Works

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

This opportunity is for the works package of Instrumentation & Monitoring of buildings & infrastructure around the proposed Old Oak common HS2 Station. This will include NR, LU, LO and 3rd party asset monitoring and instrumentation.

Scope overview

This is a package to perform instrumentation & Monitoring to both the surface and underground assets within the Old Oak Common Station site and surrounding site boundary. The purpose is to:
• Establish a baseline condition to assess behaviour of assets pre-construction.
• Control and provide confidence in the design and construction process.
• Verify that both ground and structures are behaving as predicted.
• Identify any unexpected trends, anomalies and trigger responses.
• Ensure that the impact on any existing asset does not exceed predictions.
• Safeguard existing assets.
• Enable post-construction state to be compared with initial baseline measurements if required by design.

For reference, the assets which require monitoring based on the findings of Ground Movement Asset Reports are:
• Properties on Wells House Road
• Existing Network Rail tracks and OLE Gantries
• Crossrail Operations, Maintenance and Control Building
• Crossrail tracks and other structure associated with the Crossrail depot
• Existing Retaining wall between Old Oak Common Lane and the HS2 site
• Existing Wells House Road gravity retaining wall
• UK Power Networks Cable Tunnel
• National Grid Tunnel
• IEP Depot including depot building, tracks and other structures associated with the IEP depot
• Ground surface above or close to significant buried utilities
• New HS2 structures


The indicative monitoring frequency of the listed assets will be variable, ranging from automatic, to weekly and in some instances, monthly and quarterly, depending on asset type and construction progression. Some elements of monitoring, such as Critical Rail Temperature and Track Settlement, will require real-time assessment and feedback the Employer and asset owner. It is important for respondents to this opportunity to consider their capabilities of meeting this requirement.

Interested parties must be compliant with NR standards, as well as London Underground, London Overground standards for working within their managed infrastructure. This will include supply of safety critical staff.

Current Main Works Programme:

Monitoring and instrumentation is an emerging scope, with an estimated commencement date of April 2020. A programme of works will be issued with the Invitation to Tender to shortlisted suppliers. It is likely that there will be a requirement for monitoring presence for much of the duration of the Main Contract scope (To September 2027).

Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.

The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.

What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: Commercial, Programme, Methodology, HSEQ, Capability and Capacity.

In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Terminus at Old Oak Common.


More information

Links


About the buyer

Contact name

Manish Tailor

Address

Astral House Imperial Way
Watford
WD244WW
UK

Telephone

07738982498

Email

supplychain@bbvsjv.com