Published date: 6 December 2024
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Construction work - 45000000
Architectural, construction, engineering and inspection services - 71000000
Location of contract
England
Value of contract
£178,300
Procurement reference
KENT001-DN743400-65561993
Published date
6 December 2024
Closing date
11 October 2024
Closing time
12pm
Contract start date
29 November 2024
Contract end date
28 February 2028
Contract type
Works
Procedure type
Open procedure
Any interested supplier may submit a tender in response to an opportunity notice.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
The "Folkestone - A Brighter Future" scheme seeks to 'level up' Folkestone's town centre by supporting active travel, creating a high-quality environment that supports civic pride and reverses years of disparity in investment by transforming the fortunes of the towns primary retail areas.
The requirement of this contract of works is to design and manufacture the superstructure of a pedestrian footbridge to connect Guildhall Street North to Shellons Street.
A footbridge is proposed to link Guildhall Street North and Shellons Street more-directly near the location of its pedestrian crossing, to re-establish the link which was severed by the construction of the A2033 link (Foresters Way and Shellons Street). Previously an earthwork ramp solution was considered for providing this link but due to challenges associated with this proposal, such as the impact on existing services and the level of visual intrusion it would cause, the footbridge structure was proposed by AECOM as it is considered to be a better solution.
The superstructure contractor will need to work closely with Aecom (design consultant), who are responsible for designing the substructure for the bridge to ensure that the design of the superstructure and substructure are coordinated. Two Agreement in Principle (AIP) submissions will need to be made for the KCC Structures Technical Approval Process (TAP), Aecom (as the
substructure Designer) will prepare the submission for the substructure, but the superstructure contractor will need to prepare the submission for the superstructure. It will be essential for Aecom and the superstructure contractor to work closely to ensure that the submissions are made at the same time and are co-ordinated.
More information
Award information
Awarded date
15 November 2024
Contract start date
29 November 2024
Contract end date
28 February 2028
Total value of contract
£178,300
This contract was awarded to 1 supplier.
Cake Industries
Address
Unit 2, Abbey Trading Estate, Bell Green Lane, London, SE26 5TW
Reference
None
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Contact name
Cameron Croucher
Address
Sessions House
Maidstone
ME14 1XQ
United Kingdom
Telephone
+44 3000411901
Website