Published date: 2 October 2025

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 13 June 2025, 12pm

Contract summary

Industry

  • Structural engineering consultancy services - 71312000

Location of contract

CW1 4TQ

Value of contract

£2,289,010.22

Procurement reference

CF-3210000D0O000000rwimUAA

Published date

2 October 2025

Closing date

13 June 2025

Closing time

12pm

Contract start date

24 July 2025

Contract end date

23 July 2032

Contract type

Service contract

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Leighton Hospital, built in the late 1960s and opened in 1972, is one of the most cost-effective acute hospitals and is a sister hospital to Airedale NHS Foundation Trust. Much of the original structure incorporates RAAC panels in its roof and walls, with over 16,500 roof panels and various internal and external wall panels, mostly non-load bearing. Extensive inspections and testing have been conducted, with a risk rating system (P1 to P4) applied to prioritise repairs. Ongoing remedial work includes the installation of steel frameworks, Unistrut supports, and timber reinforcements to address high-risk areas while maintaining hospital operations. RAAC management is overseen by the Estates team and supported by a detailed Structural Risk Appraisal and RAAC Management Plan.

Mid Cheshire Hospitals NHS Foundation Trust undertook a further competition for Reinforced Autoclaved Aerated Concrete (RAAC) structural engineering and survey inspection services under the NHS Shared Business Services Healthcare Planning, Construction Consultancy and Ancillary Services Framework (SBS10190), Lot 3 - Civil and Structural Engineering.

The services is required to deliver both structural engineering and surveying services, with data to be managed through a Common Data Environment provided by BIS Consult. This service will support a multi-year mitigation programme through to the hospital's planned replacement in 2032, after which the current buildings are expected to be demolished.

The contract duration will be seven (7) years, up to the anticipated demolition of the current buildings in 2032. Should demolition be delayed beyond this date, the Contracting Authority reserves the right to extend the contract accordingly, subject to mutual agreement and continued service requirements.


Award information

Awarded date

2 October 2025

Contract start date

24 July 2025

Contract end date

23 July 2032

Total value of contract

£2,289,010.22

This contract was awarded to 1 supplier.

Mott MacDonald Limited

Address

10 Fleet Place EC4M 7RB

Reference

None

Supplier is SME?

No


About the buyer

Contact name

Kiah Bouwer

Address

Middlewich Rd
Crewe
CW1 4TQ
GB

Email

kiah.bouwer@mcht.nhs.uk