Published date: 21 February 2021

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 27 October 2020, 2pm

Contract summary

Industry

  • Calculation of costs, monitoring of costs - 71244000

Location of contract

Any region

Value of contract

£10,310.69

Procurement reference

tender_198985/927205

Published date

21 February 2021

Closing date

27 October 2020

Closing time

2pm

Contract start date

10 November 2020

Contract end date

31 December 2020

Contract type

Service contract

Procedure type

Call-off from a framework agreement

A mini-competition or direct purchase from a pre-established framework agreement.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

HS2 M56 Concept Schemes
The request is to provide the HS2 engagement team with some urgent, high-level costs of construction for 7 concept designs for proposed layouts at M56 junctions 5 to 6. The level of design definition of these proposals is minimal at this stage. The information currently available is limited to a series of line sketches and a brief narrative around the scope of each concept design.
A12 / A120 Weaving Assurance
The project team would like an order of magnitude cost of construction only for this request to establish what level of confidence can be given to the costs being proposed by Costain in advance of seeking additional funds. The scope of works to price is for:
The project team have moved their preferred location for the new junction 24 further west towards junction 23. In doing this there are traffic weaving concerns due to the distance between the two junctions being less than 2 kilometres apart. A proposed mitigation measure for this issue is to build the new offline A12 westbound link between junctions 23 and 24 as a 4-lane carriageway instead of the currently proposed 3-lane carriageway for c1.25km.
A303 Sparkford to Ilchester
- Agreed DIP budget is currently £134.9m.
- SOW has been delayed by c.18 months due to external impacts.
- Project team want to test the budget with a new set of SGAR dates that reflect the delay to the SOW (please populate table below with revised dates).
- Cost Planning to re-run the budget with new dates and include an assessment costs for the prolongation of PCF Stages pre-construction.
o An apportionment of costs on a monthly burn rate could be used.
- Construction duration to remain unchanged, just moved to the right.

- Outputs to be draft, intended for internal use only.
- Output to be a Total of the Prices sheet showing the current £134.9m budget, emerging draft output and a delta column.
- This exercise is a high level test only and shouldn't be used to set any adjusted budget value.
- These numbers are intended to be for internal eyes only.


More information

Attachments


Award information

Awarded date

27 October 2020

Contract start date

10 November 2020

Contract end date

31 December 2020

Total value of contract

£10,310.69

This contract was awarded to 1 supplier.

Benchmark Estimating

Address

Manchester

Reference

No reference - other

Supplier is SME?

No

Supplier is VCSE?

No


About the buyer

Address

The Cube
Birmingham
B1 1RN
England

Email

cpspf@highwaysengland.co.uk