Published date: 2 March 2017

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 21 November 2016

Contract summary

Industry

  • Works for complete or part construction and civil engineering work - 45200000

Location of contract

Yorkshire and the Humber

Value of contract

£2,573,032.50

Procurement reference

ACGK-BLEMU3

Published date

2 March 2017

Closing date

21 November 2016

Contract start date

24 April 2017

Contract end date

22 April 2018

Contract type

Works

Procedure type

Open procedure

Any interested supplier may submit a tender in response to an opportunity notice.

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

The scope of the project for the highway improvements and environment works within the Kirkgate development area and highway boundary comprises:
• Improved accessibility for all modes to the Kirkgate development area sites
• Improved connectivity for all modes of travel
• Improved storm water drainage facilities
• Improved highway safety and the perception of safety
• Improved environment and landscaping
The "key scheme components" of the scheme comprise:
• Carriageway widening to Marsh Way to provide additional traffic lane on the approach to the roundabout
• Carriageway widening to Kirkgate to provide a priority approach to the bus stops on Kirkgate
• The subway crossings are removed and replaced with at grade toucan crossings within the signal control arrangement.

• Traffic signals installed on 3 legs of the Kirkgate roundabout

• Extensive landscaping on the roundabout and on the "boulevard" towards the Kirkgate station (Monk Street and Ingwell Street)

• Extensive paving to match the street-style design provided for the rest of the city centre and the Emerald Ring.

• New LED street lighting throughout the scheme to replace old street lighting

• Storm water drainage installed in the centre of the roundabout to cater for flood events

• Park Street opened up at the junction with Kirkgate, and new traffic signals installed.

• Monk Street closed at the junction with Brunswick Street


Award information

Awarded date

2 March 2017

Contract start date

24 April 2017

Contract end date

29 April 2018

Total value of contract

£2,573,032

This contract was awarded to 1 supplier.

Hinko Construction Ltd

Address

28 Brownroyd Hill Road
Bradford
BD6 1SA

Reference

None

Supplier is SME?

No

Supplier is VCSE?