Published date: 21 February 2021
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Calculation of costs, monitoring of costs - 71244000
Location of contract
Any region
Value of contract
£153,899.41
Procurement reference
tender_198985/927209
Published date
21 February 2021
Closing date
19 November 2020
Closing time
2pm
Contract start date
24 November 2020
Contract end date
31 March 2021
Contract type
Service contract
Procedure type
Call-off from a framework agreement
A mini-competition or direct purchase from a pre-established framework agreement.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Estimate Data review and Standardise
Non-RIS2 schemes estimates' data cleanse and migration from old tracker to MP estimates database.
1) Understand data journey made over the last couple of months and the processes currently in place for MP estimates.
2) Normalise data for the ~1.4k lines of MP estimates logged on the superseded excel tracker not currently in the MP Estimates database.
3) Sift out technical notes (ad hoc requests) and OD estimates from tracker.
4) Obtain RET extracts from SHARE or specific location on shared drives.
5) Make necessary changes to the RET collation tool to allow analysis of older versions of RETs.
6) Collate RET information from all sources RETs.
7) Validate line entries against corresponding RET information.
8) Batch import estimates information into current MP Estimates database.
Notes / caveats:
a) Where it is not possible to get source data (release email, RET, Form200, Form300) it will not be possible to validate the line entry. In this case, the entry will be submitted to the database 'as is' following the data normalising exercise.
b) There will be a requirement to liaise with Jane Searle for the sourcing of information from the commercial services division mailbox.
c) On obtaining estimates information:
i) This does not include sifting through CE folders on shared drives with a view to source RETs (or indeed peer reviews, Form200s and Form300s).
ii) If associated files are not available on SHARE or a specific location on the shared drives then we will be unable to import this in the database, and therefore will not be able to validate line entries.
iii) If associated files are stored as hard copies within the office we will not be able to validate the estimate information on the estimates tracker.
MP Estimate Data
1) MP Estimates database (continued):
a) Make the necessary changes to the database and dashboard that have been requested.
b) Develop database and dashboard further to include ability to capture and report on technical notes.
c) Updating guidance and continual support for estimating Co-ordinator.
2) Draft Scheme Budget Setting:
a) Work with HE CP to understand requirements
b) Implement reporting solution for the tracking of estimates and budgets
c) Develop dashboard for viewing budget setting information.
3) OD CP reporting solution: (separate workstream)
a) Manage solution delivery: oversee exercise and provide guidance for technical analyst responsible for solution design and implementation.
b) Provide support as and when needed.
5) Ad hoc support for Cost Planning team.
Estimating data Pipeline
The CPT require a better forward view of their pipeline of estimating work. Current management is reactive and there is a requirement to move to a proactive position to enable better planning and organisation of the team to take place.
1) Understand the data available and produce a tracking schedule/plan
2) Specify and develop engagement plan
3) Obtain stakeholder buy in and agreement of solution by
Award information
Awarded date
24 November 2020
Contract start date
24 November 2020
Contract end date
31 March 2021
Total value of contract
£153,899.41
This contract was awarded to 1 supplier.
Turner & Townsend
Address
Leeds
Reference
No reference - other
Supplier is SME?
No
Supplier is VCSE?
No
Share this notice
Closing: 19 November 2020, 2pm